Water Systems
Quick Start-Up Checklist
2150 Elmwood Avenue, Buffalo, NY 14207
Ph. 716-876-9951; Fax 716-874-8048
www.mokon.com
MOKCLST7000 2/15
Please verify that the product received matches the product ordered and that the
equipment is designed for the intended application. The following quick checklist is
an abridged version - always refer to the Mokon Manual provided for additional data
and requirements prior to the commissioning of the unit.
Electrical Inspection
Verify amp draws and voltage on serial tag match electrical service being
supplied.
All electrical termination points checked for tightness.
Electrical wiring completed and disconnect sized and installed per code and
compliance.
Motor rotation verified, motor(s) bumped.
Verify any remote control wiring is complete.
Mechanical Inspection
Mechanical fittings tight.
Unions tight.
Compression fittings tight.
Insure Supply, Drain and Process connections are connected properly and
operating pressure does not exceed ratings.
Location and Good Standard Installation Practices
Confirm safe access to equipment for maintenance, removal and lockout- tag
out.
Insure equipment is designed for the installed environment.
Allow a minimum of 4 feet (1.2 meters) on all four (4) sides to allow for
proper maintenance and operation.
Allow a minimum of 4 feet (1.2 meters) or more above unit for proper
ventilation. Please use extreme caution when dealing with hot surfaces.