Setting up the unit
23
Installation instructions
Floor without steam barrier
In the case of floors without a steam barrier, the floor plates are
screwed to the floor with the enclosed screws.
a
b
d
e
c
A
B
f
Image: A: Position of the floor plate; B: Floor plate screwed to the floor
a Cap nut
d Floor plate
b Holding plate
e Wood screw
c Stud bolt
f Equipment leg
Requirement
The floor must be capable of taking the weight of the unit
The floor must be clean and suitable for the type of fastening
The unit is set up and levelled in accordance with the planning
drawing
1. Insert the base plate of the fastening set into the holding plate in
accordance with the drawing.
2. Screw the cap nuts on hand-tight.
3. Align the floor fastening in accordance with the drawing in position
1-1 or 2-2 on the equipment leg or base frame and then mark the
fastening holes on the floor.
4. Mark the position of all the equipment legs or base frame on the
floor.
5. Using suitable lifting equipment, move the unit away until the drill
holes can be made in the floor.
6. Drill the holes in the diameter of the dowel sufficiently deep into
the floor.
7. Carefully move the unit to the installation position.
8. Unscrew the cap nuts and remove the holding plate from the base
plate.
9. Screw the base plate to the floor using the enclosed dowels and
fastening screws.
10.Ensure that, after the fastening screws have been inserted, the
floor seal is restored again.
11.Put the holding plate onto the base plate and fasten it with the cap
nuts.
12.Fill out the Commissioning report.