FIRST-RUN AND CONSIDERATIONS BEFORE FIRST-RUN
• Clean boiler internal and external parts thoroughly from dust, soot etc.
• Ensure sealing by checking smoke flue, flue and chimney cleaning covers.
• By reviewing fuel burning system according to operational principles and check whether each
element is working correctly.
• Check whether boiler explosion cover works.
• Check boiler safety systems (manometer, hydrometer, safety valve, light or audible warning
system etc.) and make sure they are working correctly.
• Boiler thermostats must be set to the appropriate value.
• After filling the installation with water, make sure all valves are on (excluding backup circulation
pump or by-pass valve). Air must be taken from air intake valves and air relief cocks in the
installation. Circulation pump should not be run during air intake.
• Ekin Endüstriyel is not responsible for the burner on the boiler. For settings related to burner
and commissioning process, contact to manufacturer company and make these processes
carried out by authorized services.
• With switches on burner electrical board, burner must be specified with a path.
• When the boiler enters the regime (1-1.5 hours after burner runs), air adjustment of burner
should be made using flue gas analysis device.
• If overheating occurs in boiler water, circulation pump must be checked (It may cycle wrong
due to incorrect electrical connections). If it is not possible to achieve any results, installation
should be checked by stopping burner.
• Monitor Gas consumption as per line pressure from the counter.