MI 3108 EurotestPV
Measurements
– a.c. LV installations
51
Perform measurement on the next socket in final ring circuit.
Commit results
(TAB key) again. The results will be committed only if they are
higher as the previous results.
The R1+RN and R1+R2
results can be cleared
with the TAB key
Repeat the measurement on all sockets of the final ring circuit.
The R1+RN and R1+R2
results can be cleared
with the TAB key
After the measurements are finished,
store
the result (optional).
Figure 5.20: Examples of Ring Continuity test
– step 2
Displayed results:
R1+RN. ......... Reference test value, committed and measured
R1+R2 ........... Reference test value, committed and measured
(r1+r2)/4 ........ Calculated reference value,
(r1+rN)/4 ........ Calculated reference value.