STEP 2
INSTALL THE INSULATED WALL PANELS
-Refer to the enclosed panel print customized for your order.
-Locate and arrange panels according to the panel print.
-Hold the first panel in place.
1.
Apply NSF approved clear silicone to the bottom of the panel.
2.
Refer to the print to position the panel and cause it to seat within
the floor angle.
-Place the second panel in place.
1.
Apply NSF approved clear silicone to the outside of the V joint
of the side panel and to the bottom.
2.
Position the panel to cause it to seat within the floor angle.
-Lock the panels together using internal cam locks.
1.
Locate cam lock wrench provided.
2.
Insert wrench into the hex head socket in the
cam lock opening.
3.
Rotate the cam lock clockwise until the lock
hooks with the adjoining panel.
4.
Continue rotating until the lock pulls the
panel together snugly as shown above.
-Continue to erect the sides and back of the chiller box.
1.
Ensure the panels are even at the top.
-Check all remaining cam locks.
1.
Tighten or re-tighten as needed.
-Press the cam lock covers (plug covers) into the holes with your hands.
NOTICE
Occasionally, a cam fastener may not operate because the hex pin
socket is broken or damaged during assembly. If one cam on a panel
fails to fasten, the remaining cam fasteners provide adequate support
and alignment for assembly of the chiller.
NOTICE
The stainless-steel panels are covered with a protective sheet of
plastic. Remove the protective plastic covering from the wall panels
as each area is completed.
WARNING
Perform the following installation steps now. The area is not accessible after the evaporator and fan
assemblies are installed.
NOTICE
DO NOT INSTALL THE DOOR PANEL AT THIS POINT. The door panel must be installed after the
coil assembly. All other wall panels must be installed before the evaporator coil assembly.