35
Pulling Conduit Through Floor Chase
1. Determine the most convenient way of routing
conduit, starting at the end which offers adequate
room for installation. The conduit installation
process requires the assistance of at least two (2)
qualified personnel.
2. Route the steel fish tape through chase opening.
Push fish tape through entire chase until it
appears at opposite end.
3. Locate an appropriate length of rope and tie to
end of fish tape (end which was routed through
chase in step 2). Approximately 2 ft (0.6 m) from
steel fish tape/rope connection, secure a swab to
rope (use mop heads or a bundle of rags for
swab).
4. Pull end of fish tape from starting point through
chase with rope and swab. The swab will clean
any construction materials, moisture, or debris
that may exist in floor chase. Continue to swab
the chase until the swab exits the chase clean and
dry.
5. After floor chase has been cleaned, remove steel
fish tape and swab from rope. Locate bundle of
beer conduit and unspool conduit to allow
unrestricted feed during installation process.
6. Locate rope through floor chase opening and
connect to proper end of beer conduit.
NOTE: The beer conduit is designed to be pulled
through floor chase in the direction of arrows printed
on conduit.
STH13_Tech.book Page 35 Wednesday, September 15, 2010 3:20 PM