PRE-DELIVERY INSPECTION
169603
35
Revision
B
J. DRAPER SEAL
a. Check deck height so that draper (A) runs just
below cutterbar (B) with maximum 1/32 in.
(1 mm) gap, or with draper deflected down
slightly (up to 1/16 in. [1.5 mm]) to create a seal.
NOTE
Measurement is at supports with header
in working position and decks slid fully
ahead.
b. Loosen tension on drapers. Refer to sub-step
F. DRAPER TENSION.
c. Lift draper up at front edge past cutterbar.
d. Loosen two locknuts (C) one-half-turn only on
deck support (D). There are two to four supports
per deck, depending on header size.
e. Tap deck (E) to lower deck relative to supports to
achieve setting recommended above. Tap
support (D) using a punch to raise deck relative to
support.
f.
Tighten deck support hardware (C).
g. Tension drapers. Refer to sub-step
F. DRAPER
TENSION.
A
B
D
C
E