Lucent Technologies ECS Minicell Battery Plant H569-420
5 - 6 Installation
Issue 5 February 1997
Cable Support
and Ground
System
Hang all cable support systems, as well as any auxiliary ground
bus bars, as dictated by the job application drawings.
Controller and
LVD Setup
Follow the controller setup procedure given in the Controller
manual to complete the steps below.
1. Wear ESD wrist strap and ground properly.
2. Enable/disable equalize charge setup
3. Enable/disable rectifier restart setup
4. Set HV shutdown level(s)
5. Set BD alarm level
6. Run office alarm wiring
7. Run other controller wiring
8. Set up other optional circuit packs
Check and set the low voltage disconnect/reconnect, if provided,
at the desired voltage level. See Figure 5-4 for the location of the
disconnect voltage select jumpers, J505.1 and J505.2 on
LVD/Fuse Board. Plug these jumpers across pins 1 and 2 of their
respective connectors to provide a disconnect voltage of
21.25±0.5 volts. To provide a disconnect voltage of 20.25±0.5
volts, plug the jumpers across pins 2 and 3 of their respective
connectors. Refer to the ECS controller manual for acceptance
testing procedures for the LVD/Fuse circuit pack and the
associated LVD/R option.
Wiring, Rectifier
Installation, and
Test
Refer to the installation and start-up procedure in the Rectifier
manual for the following steps.
•
Wire ac
•
Set up
•
Plug in
•
Test
Содержание H569-420
Страница 2: ......
Страница 7: ...Lucent Technologies ECS Minicell Battery Plant H569 420 2 List of Figures Issue 5 February 1997 ...
Страница 15: ...Lucent Technologies ECS Minicell Battery Plant H569 420 1 6 Introduction Issue 5 February 1997 ...
Страница 71: ...Lucent Technologies ECS Minicell Battery Plant H569 420 6 8 Installation Tables Issue 5 February 1997 ...
Страница 81: ...Lucent Technologies ECS Minicell Battery Plant H569 420 8 2 Spares Issue 5 February 1997 ...
Страница 85: ...Lucent Technologies ECS Minicell Battery Plant H569 420 9 4 Product Warranty Issue 5 February 1997 ...