Lucent Technologies Lineage
®
2000 ECS Battery Plant H569-416
5 - 8 Maintenance
Issue 2 August 1996
5. Reconnect quick connect leads to new contactor and then
mount new contactor using hardware from Step 4.
6. Plug P501 into J501 on LVD/Fuse board (CP5) and verify
that contactor closes.
7. Replace covers, close distribution door and verify that
“LVD FAIL” and “LVD OPEN” lights are not lit.
LVD/Fuse Board
(CP5)
Replacement
The following equipment is required:
•
standard screwdriver
Procedure: (Refer to Figure 4-3 and T-83171-31 drawing)
1. Open distribution panel.
2. Unplug the following connectors from the LVD/Fuse
Board (CP5). Leave the cables dressed.
■
P502 from J502
■
P506 from J506
■
P501 from J501
■
P504 from J504
■
TB501 from J501
3. Remove the 5 mounting screws.
4. Unplug P508 from J508 connector. Leave the cable
dressed.
5. Set jumpers J505.1 and J505.2 on replacement LVD/Fuse
Board (CP5) per H569-416 drawing for desired disconnect
voltage.
6. Reconnect P508 and J508 connector.
7. Mount the replacement board to the distribution panel
using the hardware from Step 3.
8. Reconnect the following connectors:
■
P502 to J502
Warning
Procedures in this section may cause power alarms to be
issued temporarily. Notify the alarm reporting center before
starting any replacement procedure on an operating plant.