Step I - Controller Test
Follow the controller test procedure given in the ECS controller
manual to complete the steps below.
1. Test Enable/disable equalize charge feature.
2. Test Enable/disable rectifier restart feature.
3. Test HV shutdown level(s).
4. Test BD alarm levels.
5. Test other optional circuit packs.
Step J - Load Turn-up:
Turn on and adjust all rectifiers for normal operation according
to the Rectifier manual.
Connect all loads, one at a time, by turning on the load circuit
breakers. A circuit breaker may trip immediately due to inrush
current when the plant is initially turned on. This does not
necessarily indicate a fault condition. Attempt to close the circuit
breaker a second time. If the breaker trips again, check the
wiring to the load circuit.
Step K - Converter Shelf Assembly:
Follow the Initial Start-up and Checkout procedure given in the
ECS FPS DC/DC Converter Plant manual to complete the steps
below:
1. Test PMJ and PMN alarms
2. Test MJF alarm
3. Test converters
Installation
Procedures For
Plant Growth
As your power needs evolve, equipment may be readily added to
the battery plant to provide any of the following.
•
expanded controller features
•
additional rectifier capacity
Warning
Before applying power to any individual load, follow the
powering up instructions as provided in the associated load