background image

5  /  14 

Safety

 

First 

 

F. 

TIES 

1. 

Ties should be used when the tower goes beyond its safe height

 

beyond the limits of the stabilisers/outriggers or if there is a

 

danger of instability. They should be rigid, two way ties fastened

 

to both uprights of the frame with load-bearing right angled or

 

swivel couplers. Only couplers suitable for the 50.8mm dia. Tube

 

of the tower should be used. Ideally ties should secure to 

both faces of a solid structure or by means of anchorages.

 

2. 

The tie frequency may vary depending on the application, but they should, at a minimum, be at every 4 metres height. 

3. 

For further information on tying-in a tower please contract your supplier. 

 

G.  MAINTENANCE – STORAGE - TRANSPORT 

1. 

All components and their parts should be regularly inspected to identify damage, particularly to joints. Lost or broken parts 
should be  replaced, and  any tubing  with  indentations  greater  than  5mm  should be put  to  one side  for  manufacture  repair. 
Adjustable leg threads should be cleaned and lightly lubricated to keep them free running. 

2. 

Brace claws, frame interlock clips, trapdoor latches and platform windlocks should be regularly checked to ensure they lock 
correctly 

3. 

Components should be stored with due care to prevent damage. 

4. 

Ensure components are not damaged by excessive strapping force when transported.   

 
 
 

Components 

 

Содержание Trade King 730

Страница 1: ......

Страница 2: ...to ensure your system is erected easily and safely The law requires that personnel erecting towers must be competent and qualified to do so Any person erecting a Trade King 730 mobile tower should ha...

Страница 3: ...e tie in the tower to a rigid structure when working outdoors or in exposed conditions 16 Beware of the funneling effect of open ended and unclad building 17 Debris netting or plastic sheeting should...

Страница 4: ...th vehicles e g lift trucks Do not lift pull or push the mobile scaffold tower with a lift truck 3 When moving the tower always beware of any live electrical apparatus overhead cables or moving parts...

Страница 5: ...t every 4 metres height 3 For further information on tying in a tower please contract your supplier G MAINTENANCE STORAGE TRANSPORT 1 All components and their parts should be regularly inspected to id...

Страница 6: ...6 14 Trade King 730 Aluminium Scaffold Tower Components List 600...

Страница 7: ...form height and a platform length of 1 55m has a self weight of 178kg 864 0kg 178 0kg 686 kg maximum safe working load Total weight self weight user tools and materials Example 2 A Trade King 730 towe...

Страница 8: ...and 1 0m above platforms Never stand on an unguarded platform positioned above the first rung of a tower If your risk assessment shows it necessary you may also need to guardrail platform at this leve...

Страница 9: ...to erection 3 Inspection tower prior to use 4 Tower upright and level 5 Castors locked and legs correctly adjusted 6 Diagonal braces fitted 7 Stabilisers outriggers fitted as specified 8 Platforms loc...

Страница 10: ...base unit at the base of the tower Step 1 Set up the folded base stand pre assemble Step 3 Fit one horizontal brace RED onto the bottom rung 1st rung Step 4 Fit one diagonal braces BLUE in between the...

Страница 11: ...r to horizontal as possible Step 8 Remove temporary platform from the lowest rung to the 6th rungs Step 9 Fit the temporary guardrails RED on the 8th and 10th rungs in that order on both sides of the...

Страница 12: ...n the 13th and 16th rungs Step 15 Fit another one pair of diagonal braces BLUE in opposite direction between the 17th and 20th rungs Step 16 Remove temporary platform and the guardrails from the lowes...

Страница 13: ...irection between the 21st and 24th rungs Step 21 Fit next one pair of diagonal braces BLUE in opposite direction between the 25th and 28th rungs Step 22 Fit one pair of 4 Rungs guardrail frames and ch...

Страница 14: ...thin the trapdoor You may then unlock the securing hook at the ends of the guardrail to remove them from the tower Note For further information on this product or any other products and services pleas...

Отзывы: