Safety

 

First 

 

B. 

WIND SPEED SAFETY RULES 

1. 

Beware of high winds in exposed, gusty or medium breeze conditions. We recommend that in wind speeds over 20.0 km/h, 
cease working on the tower and do not attempt to move it. If the wind becomes a strong breeze, expected to reach 31.0 km/h, 
tie the tower to a rigid structure. If the wind is likely to reach gale force, over 52.0 km/h, the tower should be dismantled. 

2. 

Wind force can be magnified by the tunneling effect of open ended building and unclad building 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

C. 

LIFTING OF EQUIPMENT 

1. 

Tower components  should  be  lifted  using  a  reliable  lifting material  (e.g. strong  rope), employing  a  reliable  knot  (e.g.  clove 
hitch), to ensure safe fastening and always lift within the footprint of the tower.

 

2. 

Assembled mobile towers should not be lifted with a crane or other lifting device.

 

 

D. 

STABILISERS / BALLAST 

1. 

Stabilisers or outriggers and ballast weights shall always be fitted when specified. 

2. 

The Quantity Schedules show the recommended stabilisation. In circumstanced where there is restricted ground clearance for 
stabilisers/outriggers, contact your supplier for advice. 

 

E. 

MOVEMENT

 

1. 

The tower should only be moved by manual effort, and only from the base. 

2. 

Do not move the mobile scaffold tower with vehicles (e.g. lift trucks). Do not lift, pull or push the mobile scaffold tower with a lift 
truck. 

3. 

When moving the tower, always beware of any live electrical apparatus, overhead cables or moving parts of machinery. 

4. 

Ensure that the platforms are free of persons and equipment and that brake locks are off prior to movement. 

5. 

Caution should be exercised when wheeling a tower over rough, uneven or sloping ground, taking care to unlock and lock 
castors. If stabilizers are fitted, they should only be lifted a maximum 25mm above the ground to clear ground obstructions. 

6. 

The overall height of the tower when being moved, should not exceed 2.5 times the minimum base dimensions, or 4 metres 
overall height. 

7. 

Before use, check the tower is still correct and complete. 

8. 

After every movement of the tower use a spirit level to check that it is vertical and level and set the adjustable legs as required. 

9. 

Do not move the tower in wind speeds over 20 km/hour .   

Beaufort 
Scale 

WIND 

DESCRIPTION 

SPEED 

In km/h. 

SPEED 

In m/s. 

GENERAL EFFECT 

ACTION 

0-3 

Light Breeze 

2-19` 

0.6-5.3`

 
 
Raises Dust 

No action required 

Moderate 

Breeze 

20-30 

5.6-8.3 

 
Loose paper,   
Twigs snap off 

Cease working on 
tower and do not 
attempt to move it 

5-6 

Strong Breeze 

31-51 

8.6-14.2 

 
Large branches in motion 
move.   
Telephone wires whistle. 

Tie the tower to a 
rigid structure 

6-8 

Gale Force 

52-75 

14.4-20.8

 
Walking progress impeded 

Dismantle tower if 
such conditions are 
expected 

Содержание Trade King 730

Страница 1: ......

Страница 2: ...to ensure your system is erected easily and safely The law requires that personnel erecting towers must be competent and qualified to do so Any person erecting a Trade King 730 mobile tower should ha...

Страница 3: ...e tie in the tower to a rigid structure when working outdoors or in exposed conditions 16 Beware of the funneling effect of open ended and unclad building 17 Debris netting or plastic sheeting should...

Страница 4: ...th vehicles e g lift trucks Do not lift pull or push the mobile scaffold tower with a lift truck 3 When moving the tower always beware of any live electrical apparatus overhead cables or moving parts...

Страница 5: ...t every 4 metres height 3 For further information on tying in a tower please contract your supplier G MAINTENANCE STORAGE TRANSPORT 1 All components and their parts should be regularly inspected to id...

Страница 6: ...6 14 Trade King 730 Aluminium Scaffold Tower Components List 600...

Страница 7: ...form height and a platform length of 1 55m has a self weight of 178kg 864 0kg 178 0kg 686 kg maximum safe working load Total weight self weight user tools and materials Example 2 A Trade King 730 towe...

Страница 8: ...and 1 0m above platforms Never stand on an unguarded platform positioned above the first rung of a tower If your risk assessment shows it necessary you may also need to guardrail platform at this leve...

Страница 9: ...to erection 3 Inspection tower prior to use 4 Tower upright and level 5 Castors locked and legs correctly adjusted 6 Diagonal braces fitted 7 Stabilisers outriggers fitted as specified 8 Platforms loc...

Страница 10: ...base unit at the base of the tower Step 1 Set up the folded base stand pre assemble Step 3 Fit one horizontal brace RED onto the bottom rung 1st rung Step 4 Fit one diagonal braces BLUE in between the...

Страница 11: ...r to horizontal as possible Step 8 Remove temporary platform from the lowest rung to the 6th rungs Step 9 Fit the temporary guardrails RED on the 8th and 10th rungs in that order on both sides of the...

Страница 12: ...n the 13th and 16th rungs Step 15 Fit another one pair of diagonal braces BLUE in opposite direction between the 17th and 20th rungs Step 16 Remove temporary platform and the guardrails from the lowes...

Страница 13: ...irection between the 21st and 24th rungs Step 21 Fit next one pair of diagonal braces BLUE in opposite direction between the 25th and 28th rungs Step 22 Fit one pair of 4 Rungs guardrail frames and ch...

Страница 14: ...thin the trapdoor You may then unlock the securing hook at the ends of the guardrail to remove them from the tower Note For further information on this product or any other products and services pleas...