Finalizing the Installation
(for qualified installers only)
© Travis Industries
6/27/2019 - 1500
864 31K CF Aust
Steps for Finalizing the Installation
1. Remove the barrier and glass (see page 40).
NOTE:
If using propane (LP) convert the appliance prior to installing the logs.
2. We recommend you purge the gas line at this time (with the glass removed). This allows gas to be detected
once it enters the firebox, ensuring gas does not build up.
3. Install the four AA batteries (see illustration below). The AA batteries act as a power backup in case the
household (AC) power goes out and are required for operation. Install three AAA batteries into the remote (see
illustration below). Synchronize the transmitter to the IFC.
4. Install the firebacks (if applicable -see page 43).
NOTE
: If no firebacks are used, make sure the media tray covers are in place (see below)
5. Install the ember chunks and ember bed glass (see page 44)
6. Install the logs (see page 48).
7. Replace the glass.
8. Start the heater.
9. Leak test all gas joints.