Operator's Manual No. 1/2015 "Alulift type Mobile Elevating Work Platform"
August 2015 Page 37
Table 6 Time limits for maintenance and inspection
Components
Before assembly
(pre-assembly review)
Every 3 months
(maintenance)
Mechanical damage to the structure
1
1
Parking brakes on the wheels
2
2
Wheels
1,2
1,2,4
Running profile
1
1
Handrails/assess handrail
1,2
1,2
Bolts and spacers
3
Drive shaft bearing
4
Diagonal and horizontal braces
1,2
1,2
Gear racks and gears
1
7
Battery chamber locking (bolts)
1,3
1,3
Service brake
2
Electrical wiring
1,8
Limit switches
2
2
Emergency lowering device battery
10
Battery
9
Labels and Manual
1,5,6
1.
Visual check
2.
Check the operation
3.
Check that they are not loose.
4.
Lubricate as needed
5.
Replace the missing or illegible label or Manual
6.
The appropriate Manual should be at the device
7.
Check the wear
8.
Check the insulation
9.
Check the voltage at the battery terminals
10.
Check the battery level
9.3.
Pre-assembly reviews
Pre-assembly reviews should be carried out by persons who assemble the PRP. The review
should consist of checking that there was no damage or deformation during transport, in
particular check the components listed in table 2.
9.4.
Maintenance Reviews.
Maintenance reviews should be carried out every
90 days (by an authorized operator). The
aim of the review is to check:
The condition of the drive mechanisms, brake systems, load-bearing structure, in
particular welded connections,
The operation of safety components and motion stops,
The operation of the controls and indicators.
The maintenance operator (operator) is obliged to:
record the maintenance review in the PRP maintenance book, stating the date and
sign confirmation of the review results and the operations carried out