Operating manual
Installation
TW160 drive
TK Aufzugswerke
61
Version 08/2021
6.6
Mounting the shift protection complying with EN81-77
1. Secure each of the shift protection devices with 2 tie bolts (Hilti HST M16/25 or
Fischer M16/25 FAZII) at the installation site.
2. Secure the shift protection devices to the bare concrete.
3. Before drilling, ensure that no reinforcing steel at the positions of the holes
hinders the drilling.
If this is the case, use one of the alternative holes that are already on the shift
protection device.
The fastening materials are included in the scope of supply. The installation
instructions of the manufacturers are to be strictly complied with!
4. Align the shift protection in such a way that the rubber elements of the shift
protection devices do not touch the machine base frame.
5. Set the clearance to a maximum of 5 mm.
The shift protection is configured for the following machine insulations:
Insulation elements without underlay for machine room without floor pavement.
In
sulation elements with underlay for machine room with floor pavement (≤ 60
mm high); underlay made from Multiplex laminated wood 140 x 140/80 / mm
high.
Fig. 6.6-1
Item Designation
Item Designation
1
Shift protection
2
Machine base frame
3
Tie bolts
4
Alternative holes
Fig. 6.6-2
max. 5 mm
Содержание TW160
Страница 1: ...OPERATING MANUAL TW160 Drive 08 2021 6234002860...
Страница 6: ......
Страница 24: ...Operating manual Technology TW160 drive TK Aufzugswerke 24 Version 08 2021...
Страница 101: ......
Страница 102: ......
Страница 103: ......
Страница 104: ...Tachogenerator RE 0444 zu SA 1 Anschlusshinweis...
Страница 107: ......
Страница 111: ...OPERATING MANUAL EMERGENCY BRAKE SYSTEMS NBS TW45 TW63 TW130 TW160...
Страница 112: ...TK Aufzugswerke GmbH Bernh user Stra e 45 73765 Neuhausen a d F Deutschland E Mail doku elevator plant de tkelevator com...