Operation 53
Charger Battery Voltage High
Charger Battery Voltage Low
The DC voltage of the battery
charger is outside the specified limits
and the charger has been turned off.
The charger will automatically restart
when the DC bus voltage returns to
within tolerance.
Make sure battery breaker is closed.
Contact Liebert Global Services if
this condition persists for more than
15 minutes.
Charger Fuse Blown
The battery circuit breaker is open or
the battery charger fuse has been
blown. The charger is no longer
charging the batteries.
Check the battery circuit breaker. If
the breaker is open, try to reset. If the
breaker will not reset or is not open,
Contact Liebert Global Services.
Charger Hardware Shutdown
Malfunction in the battery charger
section. If this condition persists
without service, the batteries can be
discharged.
Contact Liebert Global Services.
Dial Out Attempt Failed
If the unit is equipped with an internal
modem, it attempted to dial out due
to an event or command on the
modem connected to the UPS. The
attempt was unsuccessful after 3
tries.
Check the phone number
programmed into the modem. Check
the receiving modem. Check the
modem operation.
Excessive Retransfers
Attempted
Several automatic retransfer
attempts (20 attempts during 15
minutes or less) have been made to
retransfer the load from bypass (if
available) back to the UPS. The UPS
has not been able to consistently
sustain the load, because of an
overload condition or an inverter
failure. The load will remain on
bypass.
Check other messages for inverter
failure. Determine cause of the
overload and reduce the load. If the
problem cannot be corrected, call
Liebert Global Services.
Emergency off. Recycle input
to restart.
The UPS has been shut down from
an external contact (REPO) or the
front panel EPO switch.
Perform a UPS start-up procedure
when the conditions causing the
external shutdown have been
corrected. See 3.2.3 - Manual
Restart after Low Battery
Shutdown.
Fault Transferred to Bypass
The unit transferred to bypass due to
a fault or overload in the system. This
alarm accompanies the other alarms
that caused the fault.
Review other alarms. Remove
condition-causing fault if possible
(e.g., reduce overload). Call Liebert
Global Services if fault cannot be
cleared.
Ground Fault detected
on DC bus.
There is a ground fault in the battery
cabinet or battery wiring.
Contact Liebert Global Services
immediately.
Input Voltage Out-of-
Tolerance
The line to line voltage of the input
power is outside the acceptable
range. In this situation, if the voltage
is low the battery will supply power to
the critical load through the UPS.
If this condition persists the battery
will eventually completely discharge.
Check your electrical wiring. Check
with your utility.
Inverter Fuse Blown
The inverter fuse has opened
indicating a failure in the inverter
section of the UPS. The unit will
transfer the load to Bypass.
Contact Liebert Global Services
immediately.
Inverter Neutral SCR Open
On units equipped with the isolated
neutral option, the SCR has failed.
Contact Liebert Global Services.
Inverter Startup Overvolt
The inverter bus is too high during
the walk-in period. Possible fault on
the PFC.
Contact Liebert Global Services.
Table 5
Alarm Messages (continued)
Alarm Message
Meaning
Corrective Action
Содержание UPStation S3
Страница 1: ...POWER PROTECTION UPStation S3 Three Phase 12 kVA to 24 kVA 50 and 60 Hz User Manual ...
Страница 2: ......
Страница 6: ...iv ...
Страница 23: ...Installation 17 Figure 1 One Line Drawing Single Input Configuration 200 240V In Out ...
Страница 24: ...18 Installation Figure 2 One Line Drawing Dual Input Configuration 200 240V In Out ...
Страница 25: ...Installation 19 Figure 3 One Line Drawing Single Input Configuration With Neutral Isolation 200 240V In Out ...
Страница 26: ...20 Installation Figure 4 One Line Drawing Dual Input Configuration With Neutral Isolation 200 240V In Out ...
Страница 27: ...Installation 21 Figure 5 One Line Drawing Single Input Configuration 400 480 600V In 208V Out ...
Страница 28: ...22 Installation Figure 6 One Line Drawing Dual Input Configuration 400 480 600V In 208V Out ...
Страница 31: ...Installation 25 Figure 9 One Line Drawing Single Input Configuration 400 480 600V In Out ...
Страница 32: ...26 Installation Figure 10 One Line Drawing Dual Input Configuration 400 480 600V In Out ...
Страница 34: ...28 Installation Figure 12 One Line Drawing Dual Input Configuration With Neutral Isolation 400 480 600V In Out ...
Страница 35: ...Installation 29 Figure 13 Cabinet Dimensions ...
Страница 36: ...30 Installation Figure 14 Cabinet Dimensions With Transformer Cabinet ...
Страница 37: ...Installation 31 Figure 15 Connecting Terminal Details ...
Страница 38: ...32 Installation Figure 16 Connecting Terminal Details With Transformer Cabinet ...
Страница 39: ...Installation 33 Figure 17 Battery Option Details 12 Inch Cabinet ...
Страница 40: ...34 Installation Figure 18 Battery Option Details 24 Inch Cabinet ...
Страница 41: ...Installation 35 Figure 19 Field Lug Wiring Terminations ...
Страница 42: ...36 Installation Figure 20 Unloading Instructions ...
Страница 43: ...Installation 37 Figure 21 Unloading Instructions 24 Inch Battery Cabinet ...
Страница 44: ...38 Installation Figure 22 Battery Times ...
Страница 53: ...Operation 47 Figure 25 Configuration Menu Tree ...
Страница 55: ...Operation 49 Figure 26 Control Switch Locations ...
Страница 68: ...62 Features Options Figure 27 RS 232 Connections ...
Страница 69: ...Features Options 63 Figure 28 Output Distribution Panel Board ...