Ceiling Cassette Air Conditioner
Installation
1. Form the piping according to its routing. Avoid bending and
bending back the same piping point more than three times.
(This will result in hardening the pipe.)
2. After deforming the piping, align centers of the union fitting of
the indoor unit and the piping, and tighten them firmly with
wrenches.
3. Connect pipe to the service valve or ball valve which is located
below the outdoor unit.
4. After completing the piping connection, be sure to check if
there is gas leakage in indoor and outdoor connection.
After completing the piping connection, execute vacuum drying
for the connecting piping and the indoor unit.
The vacuum drying must be carried out using the service ports of
both the liquid and gas side valves.
CAUTION: Use two wrenches and
tighten with regular torque.
Outdoor
unit
Liquid side
Flare connection
Flare connection
Gas side
Indoor
unit
Spanner
Torque
wrench
Piping Connection
Vacuum drying
Flare nut fastening torque
Ø6.35mm
16±2 N.m
Ø9.52mm
38±4 N.m
Ø12.7mm
55±6 N.m
Ø15.88mm
75±7 N.m
Ø19.05mm
110±10 N.m
Grade
Liquid side piping
Gas side piping
18k
Ø6.35mm
Ø12.70mm
24k
Ø6.35mm
Ø15.88mm
30k
Ø6.35mm
Ø15.88mm
36k
Ø6.35mm
Ø15.88mm
48k
Ø9.52mm
Ø19.05mm
60k
Ø9.52mm
Ø19.05mm