Evacuating Line Set, Indoor Coil and Outdoor Unit

A

Open the liquid and vapor line service valves (counterclockwise) to release the factory nitrogen charge (contained in outdoor unit) into the

system.

B

Open both manifold valves and start the vacuum pump.

C

Evacuate the line set, indoor unit and outdoor unit to an 

absolute pressure

 of 23,000 microns (29.01 inches of mercury).

NOTE — During the early stages of evacuation, it is desirable to close the manifold gauge valve at least once. A rapid rise in pressure

indicates a relatively large leak. If this occurs, 

repeat the leak testing procedure.

NOTE — The term absolute pressure means the total actual pressure within a given volume or system, above the absolute zero of

pressure. Absolute pressure in a vacuum is equal to atmospheric pressure minus vacuum pressure.

D

When the absolute pressure reaches 23,000 microns (29.01 inches of mercury), perform the following:

Close manifold gauge valves
Close valve on vacuum pump
Turn off vacuum pump
Disconnect manifold gauge center port hose from vacuum pump
Attach manifold center port hose to a dry nitrogen cylinder with pressure regulator set to 150 psig (1034 kPa) and purge the hose.
Open manifold gauge valves to break the vacuum in the line set and indoor unit.
Close manifold gauge valves.

E

Shut off the dry nitrogen cylinder and remove the manifold gauge hose from the cylinder. Open the manifold gauge valves to release the

dry nitrogen from the line set and indoor unit.

F

Reconnect the manifold gauge to the vacuum pump, turn the pump on, and continue to evacuate the line set and indoor unit until the

absolute pressure does not rise above 500 microns (29.9 inches of mercury) within a 20-minute period after shutting off the vacuum pump

and closing the manifold gauge valves.

G

When the absolute pressure requirement above has been met, disconnect the manifold hose from the vacuum pump and connect it to an

upright cylinder of HCFC-22 refrigerant. Open the manifold gauge valve 1 to 2 psig in order to release the vacuum in the line set and indoor

unit.

H

Perform the following:

OUTDOOR

UNIT

TO VAPOR

SERVICE VALVE

TO LIQUID LINE

SERVICE VALVE

MICRON

GAUGE

VACUUM PUMP

A34000 1/4 SAE TEE WITH

SWIVEL COUPLER

500

MANIFOLD

GAUGE SET

HCFC-22

RECOMMEND MINIMUM 3/8” HOSE

Connect low side of manifold gauge set

with 1/4 SAE in-line tee to 

vapor 

line

service valve
Connect high side of manifold gauge set

to 

liquid 

line service valve

Connect  micron  gauge  available

connector on the 1/4 SAE in-line tee.
Connect  the  vacuum  pump  (with

vacuum gauge) to the center port of the

manifold gauge set. The center port line

will be used later for both the HCFC-22

and nitrogen containers.

HIGH

LOW

1

2

3

4

5

6

7

8

9

10

11 12

1/6 TURN

NITROGEN

1

CONNECT GAUGE SET

A

B

C

D

2

EVACUATE THE SYSTEM

NOTE 

— Remove cores from service valves (if not already done).

Close manifold gauge valves.
Shut off HCFC-22 cylinder.
Reinstall service valve cores by removing manifold hose from service valve. Quickly install cores with core

tool while maintaining a positive system pressure.
Replace stem caps and secure finger tight, then tighten an additional one-sixth (1/6) of a turn as illustrated.

Figure 10. Evacuating System

Содержание 13ACD-018-230

Страница 1: ...rged with dry nitrogen The unit is intended for installation in existing HCFC 22 systems Carefully follow all installation procedures Open both service valves to evacuate system This unit is construct...

Страница 2: ...ce included with outdoor unit or thermal expansion valve TXV See the 13ACD product specification sheet for approved fixed orifice sizes and expansion valve kit match ups Important The air conditioning...

Страница 3: ...K SEATED OPENED BALL SHOWN CLOSED SERVICE PORT CORE TO INDOOR UNIT TO OUTDOOR UNIT TO OPEN ROTATE STEM COUNTERCLOCKWISE 90 TO CLOSE ROTATE STEM CLOCKWISE 90 SERVICE PORT SERVICE PORT CAP STEM CAP VALV...

Страница 4: ...rnal pressure relief valve Compressor has internal vacuum protection that is designed to unload the scrolls compressor stops pumping when the pressure ratio meets a certain value or when the suction p...

Страница 5: ...ANEL MINIMUM CLEARANCE ABOVE UNIT NOTES Clearance to one of the other three sides must be 36 inches 914mm Clearance to one of the remaining two sides may be 12 inches 305mm and the final side may be 6...

Страница 6: ...ides information on replacement of existing line set If replacement line set is not required then proceed to Brazing Connections on Page 7 Refrigerant Line Set Field refrigerant piping consists of liq...

Страница 7: ...ay result in ignition of the refrigerant and oil mixture Check the high and low pressures before applying heat WARNING Allow braze joint to cool before removing the wet rag from the service valve Temp...

Страница 8: ...OM SERVICE VALVE Flow regulated nitrogen at 1 to 2 psig through the low side refrigeration gauge set into the liquid line service port valve and out of the suction vapor line service port valve CUT AN...

Страница 9: ...RVICE VALVE PREPARATION FOR NEXT STEP 7 WARNING 1 FIRE PERSONAL INJURY OR PROPERTY DAMAGE will result if you do not wrap a wet cloth around both liquid and suction line service valve bodies and copper...

Страница 10: ...H Use a field provided fitting to temporary reconnect the liquid line to the indoor unit s liquid line orifice housing LOW HIGH EXISTING INDOOR UNIT GAUGE MANIFOLD INVERTED CYLINDER CONTAINS CLEAN LI...

Страница 11: ...d end of the expansion valve and lightly lubricate the connector threads and expose surface of the Teflon ring with refrigerant oil C Attach the stubbed end of the expansion valve to the liquid line o...

Страница 12: ...unit A trace amountis a maximum of two ounces 57 g refrigerant or three pounds 31 kPa pressure Close the valve on the HCFC 22 cylinder and the valve on the high pressure side of the manifold gauge set...

Страница 13: ...nnect the manifold gauge to the vacuum pump turn the pump on and continue to evacuate the line set and indoor unit until the absolute pressure does not rise above 500 microns 29 9 inches of mercury wi...

Страница 14: ...HERMOSTAT 5 FEET 1 5M CHECK EXISTING ROOM THERMOSTAT Any excess high voltage field wiring should be trimmed and secured away from any low voltage field wiring To facilitate a conduit a cutout is locat...

Страница 15: ...system using evacuating procedure provided in this instruction 3 Use nitrogen to break the vacuum and install a new filter drier in the system 4 Evacuate the system again using evacuating procedure p...

Страница 16: ...per tension 5 Check all wiring for loose connections 6 Check for correct voltage at unit blower operating 7 Check amp draw on blower motor Motor Nameplate _________ Actual __________ Indoor Coil 1 Cle...

Отзывы: