background image

[8] 

 

Probe “P2” is inserted into the finned section of the 
evaporator coil, near the top of the unit cooler 
assembly. This probe monitors the temperature of 
the evaporator coil during the defrost cycle. The 
control is factory programmed to engage the defrost 
cycle in 4 hour intervals. The defrost cycle is set to 
run for 16 minutes, unless the temperature at “P2” 
reaches 50 degrees F prior to the end of the cycle. 
Should that occur, the temperature at “P2” will 
override and end the defrost cycle. During the 
defrost cycle, the control will display the letters 
“DE” along with the melting snowflake icon. 

Possible Displayed Alarm Codes:   

P1

” – Air probe failure: The control will override the 

“P1” functions and cycle the compressor at 5 minute 
intervals, until the probe fault can be corrected. 
 
 “

P2

” – Evaporator probe failure: The control will 

override the “P2” function and operate with a timed 
defrost cycle, until the probe fault can be corrected. 
 

HA

” – Maximum temperature alarm: The cabinet air 

temperature has exceeded programmed maximums for a 
period exceeding 15 minutes. The alarm will continue to 
display until the cabinet temperature drops below 
maximum levels.

 

 

 

LA

” – Minimum temperature alarm: The cabinet air 

temperature has dropped below the programmed 
minimum. This alarm will continue to display until the 
cabinet temperature rises above the minimum level. 
 

Note

: Should a “P1” or “P2” alarm occur, check the 

probe wire connections to the control prior to replacing 
the probe wire. 

 
For more detailed information regarding the 
electronic control programming and instructions, 
please contact: Leer Merchandiser Customer 
Service Department. Phone: 800-766-5337. Contact 
information is available on our web-site at 

http://www.leerinc.com/ice-
merchandisers/merchandiser-sales-distributors/

 

 
The defrost circuit is equipped with a defrost 
termination switch. This switch is attached to one of 
the evaporator coil tubes (located inside the unit 
cooler assembly). This switch senses temperature 
and will cycle power off to the defrost heat element 
should the temperature at the surface of the switch 
reach 70 degrees F. This switch only terminates 
power to the heat element and will not end the 
timed defrost cycle. Once the Vending Machine has 

returned to run mode, the termination switch will 
re-set when the temperature at its’ surface reaches 
35 degrees F. 
 
 
 
 

 
 
 
 

Maintenance 

 

 

 

General: 

The recommended preventive maintenance intervals 
will often vary depending upon the environment in 
which the Vending Machine operates. A preventive 
maintenance plan should be developed to aid in 
determining realistic cleaning intervals.  

Cleaning Condenser Coils:  

It is recommended to inspect and clean the 
condenser coil and fan blades every 3 month.  
There are a variety of methods available for 
cleaning the condenser coils.  Keep in mind that the 
debris is being drawn into the coil by the condenser 
fan and the debris should be removed in the 
opposite direction.  

 

The simplest and preferred method would 
involve the use of a vacuum cleaner to suck the 
debris out of the coil from the outside surface.  

 

Another method is using compressed air to blow 
dust from the coil.  The debris should be blown 
out from the inside surface of the coil.  

Note: Maintenance and repair of the electrical and 
refrigeration systems should only be performed by 
trained and qualified personnel.  

 

The defrost termination switch functions as a 
possible fire protection device. Do not remove or 
by-pass the termination switch from the defrost 
circuit. 
 
 
 
 
 

WARNING! 

Содержание VM40

Страница 1: ...er Street P O Box 206 New Lisbon WI 53950 1 800 766 5337 www leerinc com Vending Machine INSTALLATION OPERATION AND SERVICE MANUAL Scan here to be taken to the Leer Support Vending Installation page Form 1070019 01 17 ...

Страница 2: ...nding Machine at Retail Location 6 Door Locks and Sensors 6 Calibrate Scale Before Loading Ice 6 Test Transactions 6 Loading Ice 7 Stocking Instructions 7 Operating Mode Display 7 Possible Displayed Alarm Codes 8 Maintenance 8 General 8 Cleaning Condenser Coils 8 Defrosting 9 Cleaning the Vending Machine 9 Vending Machine Door Maintenance 9 Vending Calibration 9 Replacement Parts 9 Part Returns 9 ...

Страница 3: ...recycled and disposed of in an environmentally friendly manner The wooden skid is secured to the Vending Machine with hex headed screws and will require the use of a 3 8 hex socket for screw removal Vending Machine Pallet Removal 1 First remove two screws from each side perimeter board using a long 3 8 hex socket 2 Remove the six Philips screws from the front perimeter board and remove board 3 Rem...

Страница 4: ...the factory pre set cut out temperature of 16 degrees F Reporting Provision Code 3 At start up watch for and record the provision code to be displayed on the card reader Report the provision code to Vendnovation by calling 425 637 2344 Vendnovation will provision the Vending Machine and update firmware if needed Vendnovation will assign product and link to test credit card system Door Locks and Se...

Страница 5: ...ding Machine will also help ensure that the evaporator drain tube which exits the back wall is not being restricted or blocked during the defrost cycle Locate the Vending Machine so that the main power cord is within reach of an electrical outlet WARNING DO NOT use extension cords as they decrease the voltage to the unit and ultimately cause compressor failure Outdoor Vending locations shaded from...

Страница 6: ...unit does not start within a few seconds check the on off switch located next to the electronic control display The Vending Machine will continue to run until cut out temperature of 16 degrees F Door Locks and Sensors After the unit has been running for 30 minutes the doors can now be tested 3 Check the doors they should be locked 4 Turn the MODE key to the SET UP position Synchronize Inventory wi...

Страница 7: ... Set Key To initiate a manual defrost cycle press and hold the Manual Defrost Key for more than 2 seconds Note Manual defrost will not initiate if the cabinet temperature is above 40 degrees F The electronic control combines the functions of both a mechanical thermostat and a defrost timer into a single control The control also offers the consumer the capability of monitoring the operational statu...

Страница 8: ...ontact information is available on our web site at http www leerinc com ice merchandisers merchandiser sales distributors The defrost circuit is equipped with a defrost termination switch This switch is attached to one of the evaporator coil tubes located inside the unit cooler assembly This switch senses temperature and will cycle power off to the defrost heat element should the temperature at th...

Страница 9: ...s based cleaners abrasive cleaners containing chlorine bleach and any form of solvent based cleaners are not reccommended They may leave objectionable odors inside the cabinet which may be absorbed by the ice being stored in the Vending Machine Vending Machine Door Maintenance Routine inspection of the door gasket seal and the action of the door s hinges are recommended Door gaskets may mildew and...

Страница 10: ... 10 Wiring Diagram ...

Страница 11: ...pressor coil Yes Evaporator hose obstructed or kinked Defective wiring in defrost circuit Possible defective defrost heat circuit or controller Compressor functioning no ice build up on compressor coil Yes Incorrect refrigerant Wrong or low voltage Impurities in refrigerant charge Interior light functioning Yes No Defrost icon left hand of control display No Defective controller wiring Defective e...

Страница 12: ... A higher Tare weight equals less bags and a lower Tare weight equals more bags Missed sales Door sensor magnets Check door sensor magnets In set up mode hit cancel to the Hardware icon press enter press cancel repeatedly until Test Door is displayed press enter With doors closed the display should say closed Then open each door to check sensor operation Press cancel when finished to lock doors Re...

Страница 13: ...epair or replacement of any defective part s or assembly only for defects reported to Seller within ninety 90 days after the date of installation ALL LABOR CHARGES SHALL BE AUTHORIZED OR APPROVED BY SELLER PRIOR TO THE REPAIR OR REPLACEMENT OF PART S In all other events Seller shall not be responsible for any labor charges Labor charges shall only include standard straight time labor hours at the ...

Страница 14: ...Packaging of the manual before uncrating the Vending Machine Use caution when moving your Vending Machine Weight sensors are located under the Vending Machine Only use pallet jack or fork truck with care away from weight sensors ...

Отзывы: