3.4. Installation of External Heating/Cooling Devices
Based on their equipment, RHP PRO air handling units may be operated with various heating or cooling devices. Heaters/
coolers are usually installed in separate sections that are connected at the end of the unit (in the supply air stream). For air
handling units with R1 or L1 inspection sides, heater/cooler sections are mounted on an installation frame and connected at
the bottom part of the unit. For R2 and L2 inspection side units, heater/cooler sections are mounted at the top part of the
unit and must be additionally fastened or suspended (fastening/suspending accessories not included). Heat exchanger sec-
tions are mounted to the AHU and sealed in the same way as other sections (see Chapter “Connection of Sections”).
Fig. 19.
Examples for installation of heater/cooler sections