General Electrical   

7.1.1.

 

General Notes on Outside Electrical Installation  

Only qualified and competent persons should carry out any electrical installation.  Outside electrical 
installations can present dangers that are not usually encountered in internal electrical wiring. External 
equipment is subjected to the elements and attention must be made to the suitability of the cable, glands, 
connection units etc. for outside use. All cable glands should be IP66, or better. The possibility of attack by 
vermin should also be considered and adequate precautions taken.  
These notes are not intended to replace the latest I.E.E. Wiring Regulations.  

7.1.2.

 

Electrical Supply  

The electrical feed should be dedicated to the equipment and not used for any other purpose.  The supply 
should be via a suitable RCD unit backed up by either a motor rated fuse, or preferably a motor rated MCB of 
suitable rating.  
Ensure that the blower housing is protected by a suitable RCD to BS 4293 and MCB to BS 3871. Cable 
installation below ground should be SWA to BS 6346, unless otherwise stipulated.  
The RCD must be of the two-pole type rated at 25A/30mA.  (If nuisance tripping is experienced then a 
sensitivity of 100mA should be used, but this does reduce the personnel protection capability).  

7.1.3.

 

Cable Installation  

The type and size of cable depends upon site conditions and distance. If conduit/ducting is possible then 
providing mechanical and vermin attack protection is provided, single cables of adequate size can be used. 
However, the preferable method would be to use steel wire armoured (SWA) cable.  This should be buried in 
the ground at a depth of 600mm laid on sand with warning tapes on the cable and an additional tape at a 
depth of 150mm.  
For loads up to 0.75kW and runs of less than 100 metres, 2.5mm² 3 core SWA is adequate. For loads up to 
1.55kW and runs of less than 100 metres, 4.0mm² 3 core SWA should be used. It is a requirement to use the 
unused core in the cable for the earth conductor and this should be sleeved with earth sleeving at both 
connection points.

 

 

General Installation  

The control panel must not be adjacent to the plant. It can be mounted in the blower housing (supplied with 
Biotec / BioFicient / Biosafe Units), wall mounted or fixed to the mounting frame (available separately). It 
should be positioned so it cannot be reached by someone standing in or on the unit.  It would be advisable to 
situate the control panel and beacon in a frequently viewed position, so if a fault alarm appears it will be seen.  

7.2.1.

 

Mounting Frame Installation (where applicable)  

Set the frame legs in a concrete base, minimum 250mm thick and prop the frame to prevent movement until 
the concrete has set.  
Allow 350mm minimum clearance from finished ground level to the bottom of the panel. 

7.2.2.

 

Retrofit of Control Panel  

This Panel can replace the Kingspan Panel (P.No. 010086 - Green Panel). The existing beacon (P.No. 010332) 
will have to be replaced with the New Beacon (P.No. 1009254) which is provided with Control panel (P.No. 
1002510) as it is not compatible with the new control panel. 

 

Installation of Integral Discharge Pump (where applicable) 

 

Using a suitable M20 gland, feed the pump power cable through Gland Hole and terminate to connections 1 & 
2 (J6) according to Figure 3 & Figure 4. 

 

Installation of High-Level Alarm 

 HLA (where applicable)  

 

Fix the black plastic bracket to the side wall of the baffle (the exact position is on the drawing included with 
the HLA kit). Secure the float cable in the cable gland as shown on the drawing in the HLA kit. Pull the float 
cable through any installed ducting into the blower housing. Complete wiring according to Figure 3 & Figure 4. 

Содержание Klargester 1002510

Страница 1: ...Kingspan Klargester 1011026 Domestic Wastewater Control Panel USER MANUAL...

Страница 2: ...Installation of High Level Alarm HLA where applicable 6 Beacon units P No 1009254 where applicable 7 Installation of High Level Alarm HLA where applicable 7 For Biotec Bioficient or BioSafe Applicati...

Страница 3: ...of Practice Statutory Requirements and any specific instructions issued by the supplier of these details Earthing All equipment must be earth bonded in accordance with the latest IEE Wiring Regulation...

Страница 4: ...1011026 User Manual Issue 01 26 10 2021 4 7 Installation Figure 1 1002510 Lid Cover Figure 2 Enclosure Mounting Dimensions Figure 3 Control Panel Wiring 1...

Страница 5: ...1011026 User Manual Issue 01 26 10 2021 5 Figure 4 DTP Control Panel Wiring 2...

Страница 6: ...tape at a depth of 150mm For loads up to 0 75kW and runs of less than 100 metres 2 5mm 3 core SWA is adequate For loads up to 1 55kW and runs of less than 100 metres 4 0mm 3 core SWA should be used I...

Страница 7: ...Applications 7 7 1 Power Pressure Failure Detection System PPFDS where applicable The panel is designed to be used in conjunction with the Beacon unit to provide warning of either loss of power or ai...

Страница 8: ...te socket below the battery on the PCB marked J3 After finishing wiring replace the isolator cover and screw Turn the mains supply on at the source Turn on the panel using the isolation switch It shou...

Страница 9: ...vation time Alarms The conditions shown below cause an alarm message to appear on the display the beeper sounds the beacon flashes and the common alarm telemetry relay is de energised Some alarm condi...

Страница 10: ...factory defaults This menu is intended for use by installation Service engineers only The menu is entered by simultaneously pressing then releasing the three buttons On entry to the menu all outputs...

Страница 11: ...4 hour format The display will show Figure 13 Date Time Use and to move between date and time Pressing the button will freeze display of the clock and enter edit mode to allow the date or time to be s...

Страница 12: ...ickle Charge indicates that the unit is fully charged and maintaining the battery 8 6 7 Factory Defaults This option allows the control unit to be set back to the defaults as they were when the unit l...

Страница 13: ...lower J9 Chemical dosing pump Grundfos KP 350 Grundfos KP 250 Secoh JDK 250 Kingspan 404390 Fusing F1 De sludge pump terminals 3 4 T 5A H 250V F2 Internal power supply unit T 2A H 250V F3 Motor blower...

Страница 14: ...y 16 x 2 character LCD Green power LED Real Time Clock Event log timestamps and controlling the operation of the motors blowers according to a timetable LED Beacon 1009254 Only the LED beacon 1009254...

Страница 15: ...ay Motor Blower Start Time Time of Day where Unit is started 00 00 00 Stop Time Time of Day where Unit is stopped 23 59 59 Run Time Time for the components to Run 23 59 59 24 hours Pause Time Time for...

Страница 16: ...1011026 User Manual Issue 01 26 10 2021 16 This Page Intentionally Left Blank...

Отзывы: