017904-04 BioFicient 4-6 Installation Manual
12
BioFicient® IPS HLA Installation
100mm
Cable Gland
250mm
High Level Alarm
Float
1.
Remove the loose float, pivot weight & cable gland
located in the blower housing.
2.
Drill Ø20mm hole & fit cable gland in position
shown above the Final Settlement Tank (FST).
3.
The bottom of the float to be approx. 250mm from
the top of the pivot weight.
4.
Pass the float cable through the cable gland and
align the top of the pivot weight with the top of
the FST. Tight the cable gland up.
5.
Ensure the operation of the float will not foul on
any pipework.
High Level Alarm
19mm Air Diffusers
Hose Connection
6.
If required, float cable to be extended to control
panel.
7. On All types of plant. Connect hoses to Sludge
Recycle and Diffusers.
Final Settlement Tank
13mm Sludge recycle