Keysight N5227B Service Guide 7-45
Repair and Replacement Procedures
Removing and Replacing the A37 Reference Mixer Switch
Removing and Replacing the A37 Reference Mixer Switch
Tools Required
— T-10 TORX driver (torque to 9 in-lb or 1.02 N.m)
— T-20 TORX driver (torque to 21 in-lb or 2.38 N.m)
— 5/16 inch open-end torque wrench (torque to 10 in-lb or 1.13 N.m)
— ESD grounding wrist strap
Removal Procedure
Refer to
for this procedure.
1.
Disconnect the power cord.
2.
Remove the outer cover. Refer to
“Removing the Covers” on page 7-6
3.
Position the analyzer bottom side up.
4.
Disconnect four semirigid cables (item
①
) from the A37 reference mixer
switch.
5.
Remove two screws (item
➁
) that secure the A37 reference mixer switch
to the side of the test set deck.
6.
Move the disconnected semirigid cables out of the way and lift the A37
reference mixer switch and mounting bracket out of the analyzer. It may
be necessary to loosen the connector at the other end of some of the
semirigid cables to allow them to be moved enough.
7.
Disconnect the wire harness cable (item
③
) from the A37 reference mixer
switch.
8.
Remove two screws (item
④
) that attach the A37 reference mixer switch
to its mounting bracket.
Replacement Procedure
1.
Reverse the order of the removal procedure.
When reinstalling the A37 reference mixer switch into the analyzer, loosely
install the two mounting screws (item
➁
). Connect the four semirigid
cables (item
①
) and torque the connectors to 10 in-lbs, then tighten the
two mounting screws (item
➁
).
2.
Perform the post-repair adjustments, verifications, and performance tests
that pertain to this removal procedure. Refer to
.
Be careful not to damage the center pins of the semirigid cables. Some
flexing of the cables is necessary to remove the assembly. However, do not
over-bend the semirigid cables.
Содержание N5227B
Страница 26: ...2 8 Keysight N5227B Service Guide General Product Information Keysight Support Services and Assistance 2...
Страница 176: ...5 40 Keysight N5227B Service Guide Theory of Operation Receiver Group Operation 5 Figure 5 17 4 Port Receiver Group...
Страница 177: ...Keysight N5227B Service Guide 5 41 Theory of Operation Receiver Group Operation Figure 5 18 2 Port Receiver Group...
Страница 184: ...5 48 Keysight N5227B Service Guide Theory of Operation Power Supply Group Operation 5...
Страница 189: ...Keysight N5227B Service Guide 6 5 Replaceable Parts Rebuilt Exchange Assemblies Figure 6 1 Module Exchange Procedure...
Страница 203: ...Keysight N5227B Service Guide 6 19 Replaceable Parts Replaceable Parts Listings Figure 6 6 Top Assemblies All Options...
Страница 217: ...Keysight N5227B Service Guide 6 33 Replaceable Parts Replaceable Parts Listings Figure 6 12 Bottom RF Cables Option 201...
Страница 221: ...Keysight N5227B Service Guide 6 37 Replaceable Parts Replaceable Parts Listings Figure 6 14 Bottom Assemblies Option 205...
Страница 237: ...Keysight N5227B Service Guide 6 53 Replaceable Parts Replaceable Parts Listings Figure 6 21 Bottom RF Cables Option 219...
Страница 241: ...Keysight N5227B Service Guide 6 57 Replaceable Parts Replaceable Parts Listings Figure 6 23 Bottom Assemblies Option 220...
Страница 255: ...Keysight N5227B Service Guide 6 71 Replaceable Parts Replaceable Parts Listings Figure 6 29 Bottom Assemblies Option 401...
Страница 263: ...Keysight N5227B Service Guide 6 79 Replaceable Parts Replaceable Parts Listings Figure 6 32 Bottom Assemblies Option 405...
Страница 267: ...Keysight N5227B Service Guide 6 83 Replaceable Parts Replaceable Parts Listings Figure 6 33 Bottom RF Cables Option 405...
Страница 271: ...Keysight N5227B Service Guide 6 87 Replaceable Parts Replaceable Parts Listings Figure 6 35 Bottom Assemblies Option 410...
Страница 279: ...Keysight N5227B Service Guide 6 95 Replaceable Parts Replaceable Parts Listings Figure 6 38 Bottom Assemblies Option 419...
Страница 318: ...6 134 Keysight N5227B Service Guide Replaceable Parts Replaceable Parts Listings 6...