2.1. Installation instructions

The grease separation plant is supplied complete in pre-as-

sembled units. Under normal circumstances, the equipment

is set up by a plumber or can, if requested, be installed by a

KESSEL technician for an agreed upon fee. 

When installing the plant, the following must be observed 

1. The safety instructions on Page 4 must be followed.
2. The  instructions  on  the  packaging  must  be  taken  into  ac-

count!  No  non  approved  parts  of  the  separator  should  be
used to move or lift the separator during transport or instal-
lation.

3. The grease separation plant must be checked for transport

damage immediately on arrival.

4. The technical data relating to your plant will be found on the

serial plate on one of the tanks and the electrical data will be
found on the serial plate attached to the control unit. All data
are recorded in these instructions as well the plant pass.

Documents  relating  to  the  equipment  are  included  at  the
back of the instructions.

5. Bad  odours  will  be  released  if  the  plant  or  barrels  are  not

handled properly or maintenance work is not carried out in
the proper manner. For this reason, we recommend installing
the grease separator in a separate room with suitable venti-
lation (such as a fan). It is also advisable to install the grease
separator in a tiled room with at least one floor drain and a
hot water supply in order to ease maintenance and cleaning
work. The height of the room must be sufficient for work to
be  carried  out  at  the  maintenance  ports  (minimum  30  cm
from the ceiling). The width of the room should allow for a
working space of about 1 m on all sides.

6. In the case of rooms with restricted access, the tanks can be

dismantled  and  reassembled  (see  exploded  diagram  on
Page 14).

7. Be sure that the maximum allowable floor loading in the room

of installation is not exceeded (see weight table).

8. The plant must be installed on a level surface in a frost free

area. 

9. In order for the separator to function properly the tempera-

ture in the room of installation should not be below 15 de-
grees Celsius.

10. The service side is pre-assembled at the factory in accor-

dance with the order. This can be altered on site. (See as-
sembly instructions). Assemble the plant components using
the  connection  elements  supplied  with  the  equipment.
(Screw  the  tanks  together  using  a  maximum  torque  of  7
Nm).

11. The inlet and outlet of the separator feed and discharge pipe

must be connected on-site. Do this in accordance with the
standards DIN 1986.

12. The fall / drainage pipes to the inlet of the separator should

have at least a 1 meter long horizontal run with a slope of at
least 1:50 before entering the separator. The transition from
the  fall  pipe  to  the  calming  stretch  must  be  constructed
from two 45 degree bends.  

This reduces

the risk of the siphon and siphon trap being sucked empty.

the amount of air admitted to the system, air movements and
build-up of bad odours

the formation of foam in the separator.

If  the  separator  plant  is  installed  below  the  local  backwater
level,  a  wastewater  lifting  station  must  be  installed  in  accor-
dance with DIN 1986, providing local regulations do not requi-
re otherwise. Lifting units must also be provided with their own
ventilation pipe. 

Important  on-site  requirements  for  proper  function  and
odour free grease separator operation:

Grease separator plants and their feed and discharge pipes
must be provided with sufficient ventilation in accordance
with DIN EN 1825-2. Consequently, as a ventilation pipe, the
feed must be taken above the roof. All pipes connected to
the plant that are more than 5 m long must be ventilated se-
parately. If the main wastewater pipe to the separator is lon-
ger than 10 m and not separately ventilated – then this pipe
must also be ventilated.

In order to avoid the build up of bad odours, the feed and di-
scharge pipe connections must be firmly connected and all
seals must be fitted carefully.

All  drainage  fixtures  connected  to  the  grease  separator
should be equipped with odor traps and sludge traps. Large
items  such  as  utensils,  ketchup  /  mustard  wrappers  and
bones etc will cause the separator, pumps and valves to mal-
function.

2.2 Assembly

1. Grease and sludge separator components

Set up the grease separator tank (10a) and the sludge separa-
tor tank (11a)

Connect the drainage hoses (10b and 11b) to the sludge dis-
posal port (4a) and to the grease disposal port (6a)

Connect the ventilation hoses (10c and 11c) to the connection
port on the sludge and grease storage barrel covers

 

   

 

   

 

   

 

   

Содержание SE M NS 10

Страница 1: ...dling Frequent disposal of freshly collected grease and sludge into connected storage tanks even during separator operation Separate disposal collec tion of grease and sludge Smooth wax like surface p...

Страница 2: ...ot to be climbed on as a means of reaching other installations Use separate ladders etc for this purpose Because of the possible formation of bio gasses SMOKING IS PROHIBITED while the separator is op...

Страница 3: ...lacement parts Page 21 10 Maintenance and servicing checks Page 22 11 Maintenance instructions for SE separators Page 22 12 Warranty Page 23 13 Declaration of Conformity Page 24 14 Manufacturer Separa...

Страница 4: ...te is its method of disposal While conventional separators must be emptied completely and shut down while this work is carried out in the case of the SE only the ma terial which has been separated out...

Страница 5: ...d is later drained into the collection and transport barrels Disposal of the material in closed barrels is achieved with almost no smell When changing the barrels there may be a temporary release of o...

Страница 6: ...0 4100 4600 Separator in Liter 2950 l 3650 l 4350 l NS NS 15 NS 20 NS 25 b1 1650 1750 1850 x Dimensions Weight in kg 97 128 186 192 Art Nr 93202 00 SE1 CNS 93204 00 SE1 CNS 93207 00 SE1 CNS 93210 00 S...

Страница 7: ...der This can be altered on site See as sembly instructions Assemble the plant components using the connection elements supplied with the equipment Screw the tanks together using a maximum torque of 7...

Страница 8: ...tor ventilation Ventilation pipes should be connected directly to outdoor ambient air roof The venti lation pipes should not be connected to one another 2 3 Control unit mounting The main power switch...

Страница 9: ...the operation of the separator Grease separator disposal company 2 Preparation for the hand over and initial training All sanitary connections must be complete Completely filling the separator with c...

Страница 10: ...before disposal During the last minute of heating the mixing motor should also run If the automated heating times are changed the mixing times should be changed accordingly 4 4 Setting parameters Note...

Страница 11: ...ow sludge transfer can cause the grea se separator area to be pumped out Automatic rinsing Automatic rinsing is triggered via a time switch For this rea son leave the valve on the rinsing line 1c open...

Страница 12: ...drainage will have enough room in the collection tank and place onto the empty barrel and connect Place the closed cover onto the full collection barrel and se cure properly Mark the barrel to identi...

Страница 13: ...h transparent hose and ventilation connection Ventilation connec tion port Drainage inlet Center of cover for inlet and ventilation Threaded cover for twist tigh tening Operational covers are custom d...

Страница 14: ...6 Explosio 1a 1b 1c 3a 3b 4a 4b 3c 5a 2a 2b 2c 6a 9a 9b 9c 9d 2f 2e 2d 1 1a 1 1b 1 1c 1 1d 14...

Страница 15: ...ase separator Tank seal gasket Heating dome Grease discharge valve Mixer Grease discharge cover Cover seal gasket Compensation tank Ventilation pipe Control unit Pump cables Heating dome cables Mixer...

Страница 16: ...replacement part number Danger symbol Protection category CE symbol Disposal information do not dispose of control unit in household trash Control unit hardware id The control unit ID sticker is loca...

Страница 17: ...17 7 Control unit...

Страница 18: ...ome 230 V single phase 50 Hz 1200 Watt Mixing motor 230 V single phase 50 Hz 180 Watt Rinsing motor 230 V single phase 50 HZ max 750 Watt Heating rod 230 V single phase 50 Hz max 1500 Watt IP 54 C 16...

Страница 19: ...the sludge trap tank Ensure that the sludge trap tank is filled to its upper edge with water Build up of layer of floating sludge layer Discharge floating sludge during each dispo sal Gradual build up...

Страница 20: ...per operating condition Install ventilation pipe or increase size of existing ventilation pipe Check barrels barrel covers and pipe connections to barrels Check all hoses and hose connections Remove f...

Страница 21: ...F Lifting Station KESSEL offers various lifting stations which can be installed before or after the grease separator Please note that a twin pump lifting station should be installed after a grease sep...

Страница 22: ...anual The results of the general inspection should be documented Any irregularities defects or problems with the separator should also be documented and repaired immediately 11 Maintenance instruction...

Страница 23: ...rresponding norms regulations 2 Wear and tear on a product will not be considered a defect Problems with products resulting from improper installation handling or maintenance will also not be consider...

Страница 24: ...24...

Страница 25: ...ecked for watertightness to be sure that it is fully operational before leaving the factory Date Name of examiner Mat Description Mat No Order No Prod Date Ref No Material Weight EN Approval Dimension...

Страница 26: ...plumbing company __________________________________________________________ Address __________________________________________________________ Telephone Fax __________________________________________...

Страница 27: ...operating instructions Initial operation and instruction were not carried out The client person responsible for initial operation was handed the following components and or product components Initial...

Страница 28: ...ifting Stations and pumps K Drains and shower channels K Separators Grease Separators Oil Fuel Coalescence Separators Starch Separators Sediment Separators K Septic Systems K Inspection Chambers K Rai...

Отзывы: