Installation
Field piping
To ensure satisfactory operation and performance, the following points should be noted for field piping
arrangements:
Pipework routes must be as simple and as short as possible.
Avoid low points on pipework where oil can accumulate.
Use only clean, dehydrated refrigeration grade copper tube with long radius bends.
When brazing use only silver alloy rods.
Run braze without over filling to ensure there is no leakage into the tube.
To prevent oxidization, blow oxygen free nitrogen through pipework when brazing.
Protect the casing of the unit when brazing connections.
Install insulation with a minimum wall thickness of 3/8” on both liquid and suction lines.
Adequately support all pipe work at a maximum of 2 metre intervals.
Use of incorrect pipe sizes can affect system pressures/temperatures and gas velocity for proper oil return.
Important Note:
One of the main factors affecting equipment reliability and compressor service life is refrigeration
circuit contamination. During installation, circuit contamination can be caused by:
Brazing & Welding Oxides
Filings & Particles from de-burring pipework
Brazing Flux
Moisture & Air
Important Note:
Pipe sizes and maximum lengths/heights should be strictly as per the information given on page 4. All
local codes of practice must be observed in the installation of refrigerant piping
Содержание JCC2
Страница 1: ...JCC2 CELLAR AND PRODUCT COOLERS ISSUE 01 02 2016 CELLAR COOLER RANGE TECHNICAL MANUAL ...
Страница 17: ...Issue 01 02 2016 Page 17 Drawings Indoor unit dimensions 25E 40E ...
Страница 18: ...Issue 01 02 2016 Page 18 Drawings Indoor unit dimensions 50E 60E ...
Страница 24: ...Issue 01 02 2016 Page 24 Certification ...
Страница 25: ...Issue 01 02 2016 Page 25 THIS PAGE IS LEFT BLANK INTENTIONALLY ...