12.0 INSTALLATION
12.1 POSITIONING
After unpacking the equipment and preparing the compressor room, put the machine into position,
checking the following items:
ensure that there is sufficient space around the machine to allow maintenance (see Fig. 11).
ENSURE THAT THE OPERATOR CAN SEE THE WHOLE MACHINE FROM THE CONTROL
PANEL AND CHECK THE PRESENCE OF ANY UNAUTHORIZED PERSONS IN THE
VICINITY OF THE MACHINE.
12.2 ELECTRICAL CONNECTION
Check that the supply voltage is the same as the value indicated on the machine data plate.
Check the condition of the line leads and ensure that there is an efficient earth lead.
Ensure that there is an automatic cut-out device upstream for the machine against overcurrents,with a
differential device (see Ref. 1 wiring diagram).
Connect the machine power cables with the greatest care, according to the local standards in force.
These cables must be as indicated on the machine wiring diagram.
Connect the cables to the charging clamps on the electric panel and make sure they are properly
tightened. After the first 50 working hours, check that the screws on the electric terminals are tight.
ONLY PROFESSIONALLY SKILLED PERSONNEL MAY HAVE ACCESS TO THE ELECTRIC
PANEL. SWITCH OFF THE POWER BEFORE OPENING THE DOOR OF THE ELECTRIC
PANEL.
COMPLIANCE WITH THE REGULATIONS IN FORCE CONCERNING ELECTRIC PLANTS IS
FUNDAMENTAL FOR OPERATOR SAFETY AND FOR THE PROTECTION OF THE
MACHINE.
12.3 CONNECTION TO THE COMPRESSED AIR NETWORK
Fit a manual isolation valve Ref. 2 Fig. 11 between the machine and the compressed air network so
that the compressor may be isolated during maintenance operations.
Condensate must be drained Ref. 3 Fig. 11 from the oil receiver (manually) in conformity with the local
regulations in force.
ALL DAMAGE DUE TO THE FAILURE TO COMPLY WITH THESE INDICATIONS CANNOT
BE ATTRIBUTED TO THE MANUFACTURER AND MAY CAUSE INVALIDITY OF THE
WARRANTY CONDITIONS.
FIG. 10
FIG. 11
Protect the power cable with a suitable
channel.