U-MATCH AIR CONDITIONERS INSTALLATION
51
Sponge (gray)
Drain hose
Clamp
Clamp(attachment)
Sponge(attachment)
Below 4mm
Figure 1-1-9
2
˅
Testing of Drainage System
After the electrical installation is completed, carry out the testing of the drainage system.
During the test, check if the water correctly flows through the pipelines. Carefully observe the joints to
ensure that there is no leakage. If the unit is to be installed in a new house, carry out testing before decorating
the ceiling.
3
˅
Matters of Attention
The joint of Drainage Pipeline must not have leakage.
The Drainage Pipeline shall be installed with an inclining angel of 5
̚
10°, so as to facilitate the drainage of
condensate. The joints of the Drainage Pipeline must be covered by thermal insulation materials to avoid
generation of exterior condensate. (As shown in Figure 1-1-10)
㇑ⴆ
ߧࠍ≤㇑؍ቲ
Figure 1-1-10
1.1.7 Installation of air pipes and openings
Caution:
The air supply pipe, the air intake pipe and the fresh air pipe must be covered with a layer of thermal
insulation, so as to avoid thermal leakage and condensation. Firstly apply liquid nail on the pipes, then attach
the thermal insulation cotton with a layer of tinfoil. Use the liquid nail cover to fix it. Lastly use tinfoil
adhesive tape to carefully seal the joints; other good thermal insulation materials can also be used.
The air supply pipes and the air intake pipes shall be fixed to the prefabricated boards of the ceiling by using
Insulating layer of condensate pipe
Pipe cover
Содержание u-match on/off
Страница 1: ......
Страница 4: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 1 PRODUCT...
Страница 24: ...U MATCH AIR CONDITIONERS PRODUCT 21 5 PIPING DIAGRAM...
Страница 25: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 22 CONTROL...
Страница 26: ...U MATCH AIR CONDITIONERS CONTROL 23 CONTROL 1 OPERATION FLOWCHART 1 1 Cooling Dry Operation...
Страница 27: ...U MATCH AIR CONDITIONERS CONTROL 24 1 2 Heating Operation...
Страница 45: ...U MATCH AIR CONDITIONERS CONTROL 42 5 2 4 Dimensions...
Страница 48: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 45 INSTALLATION...
Страница 91: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 88 MAINTENANCE...
Страница 97: ...U MATCH AIR CONDITIONERS MAINTENANCE 94 Malfunction display E1 Compressor High Pressure Protection...
Страница 98: ...U MATCH AIR CONDITIONERS MAINTENANCE 95 Malfunction display E3 Compressor Low Pressure Protection...
Страница 101: ...U MATCH AIR CONDITIONERS MAINTENANCE 98 Malfunction display E6 Communications Failure...
Страница 107: ...U MATCH AIR CONDITIONERS MAINTENANCE 104 2 ULS 12 WITH FUNCTION OF LOW TEMP COOLING WITHOUT FUNCTION OF LOW TEMP COOLING...
Страница 108: ...U MATCH AIR CONDITIONERS MAINTENANCE 105 3 ULS 18 WITH FUNCTION OF LOW TEMP COOLING WITHOUT FUNCTION OF LOW TEMP COOLING...
Страница 109: ...U MATCH AIR CONDITIONERS MAINTENANCE 106 4 ULS 24 WITH FUNCTION OF LOW TEMP COOLING WITHOUT FUNCTION OF LOW TEMP COOLING...
Страница 111: ...U MATCH AIR CONDITIONERS MAINTENANCE 108 6 ULT36 WITH FUNCTION OF LOW TEMP COOLING WITHOUT FUNCTION OF LOW TEMP COOLING...
Страница 112: ...U MATCH AIR CONDITIONERS MAINTENANCE 109 7 ULT 45 WITH FUNCTION OF LOW TEMP COOLING WITHOUT FUNCTION OF LOW TEMP COOLING...
Страница 115: ...U MATCH AIR CONDITIONERS MAINTENANCE 112...
Страница 163: ......