Appendix B Director Switch Cable Management
This example explains cabling a Director switch in a raised floor cable management
scenario.
1. Cable the Leaf modules from the top rows of the chassis down toward the floor.
2. Cable each Leaf from the bottom row up to the top row, and from the inside port
(nearest the fan units) to the outside port.
Figure 71.
Leaf Cabling
3. Use Velcro ties to wrap the cables for each leaf module.
4. Hang the tied cables over the cable management bracket.
Figure 72.
Using Velcro Ties and the Cable Management Hanger
5. Tie off all of the cables (red band in Figure 73 below) before feeding the cables
under the floor.