Installation / Assembly
T-Rack
®
3.0 Series
– Assembly Instructions 1.1(2019-03) E inge
Page 47 of 84
© inge GmbH
5.7.2
Mounting the Module on the Channel Section (DIN 1026)
Step
Activity
Figure
1
Screw the threaded pins (DIN 913) M10 x 50 into the bottom
T piece
Using a hex key (size 5), screw the two threaded pins (DIN 913)
M10 x 50 all the way into the two threaded holes of the middle
rib.
2
Position and mount the module on the channel section (DIN
1026)
Number of persons: 3
ATTENTION
Always start with the first module on the
longer side of the frame.
a)
Remove the protective caps from the T pieces at the top
and bottom.
b)
Now lift the module vertically over the first bottom
connecting brace of the frame.
c)
Lower the module until both threaded pins (DIN 913) M10 x
50 on the lower T piece are inserted in the two holes in the
channel section (DIN 1026). The front edge of the T piece
and the front edge of the frame must be flush.
back
front
= actual
1