BOILER ROOM AIRING

There are three reasons for fresh air in boiler rooms.
1.The burning air needed for the burning in the boiler
2.The air needed for prevention of dirt and dust,for releasing the gases and fuel to put out
3.The air needed for overheating in the boiler room.

Airing for first two reasons are continously needed.The thirs one is needed 
especially for the boilers which are working on summer time.
Maximum temperature for the boiler room must be 32 °C
Boiler room must be protected against freezing.

If the fuel is 

natural gas 

Boiler 
Type

*    If natural airing system is used. ** Ventilating aring 
      system is used

***

Bottom

Up

Bottom

Up

***Bottom value shows the clean air input up shows the

OM 06

1.971

985

1.224

816

      air output.

OM 07

2.285

1.142

1.450

967

OM 08

2.546

1.273

1.639

1.093

OM 09

2.808

1.404

1.827

1.218

OM 10

3.017

1.509

1.978

1.319

OM 11

3.253

1.626

2.147

1.432

OM 12

3.488

1.744

2.317

1.545

OM 13

3.750

1.875

2.505

1.670

OM 14

4.011

2.006

2.694

1.796

OM 15

4.221

2.110

2.844

1.896

OM 16

4.456

2.228

3.014

2.009

CHECKINGS AND STARTING THE BOILER

Pre Controls

Following  controls must  be  done  before starting the boiler. If there are any problems  or failure, boiler 
must not be started.
Water level of the boiler  must be controlled. Water must be  added to the boiler if the water level is low.
Please  call   technicians  if there is a water leakage. Leakage must be prevented before starting the
boiler. If there is a leakage in the plumbing system,boiler must be started after repair.
Flue  connections must be controlled. Boiler must  not be started before repairing the connection if there 
is a problem.
Area must be properly air conditioned.
Gas valves must be checked as if they are on if gas fuel is used in the boiler.
Liquid  fuel level of the tank must be  controlled and  fuel valve  must  be opened if  liquid fuel is used in
the boiler. Fuel - burner connection must be controlled.If there are any problems filters must be cleaned.
Working and the directions of the pumps must be controlled. 
Electric ssytem of the control panel must be controlled.
All water and gas valves of the boiler must be opened.
All other connections must be controlld according to the system options.

Starting The Boiler

Turn the main electric switch of the boiler room on. Working lamp will be on.
Start the circulation pump
Turn the ''on / off '' switch of the burner to the mode ''on'' (Check the burner instructions manual.)
The indicator light will be on .

**Volume of Air 

*Net Cross Section of 

Needed for Force Airing

 ( m³/h )

Open for Natural Airing

 ( cm² )

Содержание 0M 08

Страница 1: ...Oil Gas Fired Boiler Cast iron Triple Pass Design 378 kW to 930 kW...

Страница 2: ...G 34 CLEANING THE BOILER 35 BURNER DOOR AND BURNER CONNECTION 36 BURNER CONNECTION FLANGE SIZES 37 INTRODUCTION In this manual you will find the instructions for three pass cast iron boilers suitable...

Страница 3: ...Starting and first operation of the boiler must be made by authorized technicians The periodical controls of the boiler and the burner must be done If not the boiler can lose efficiency and the fuel...

Страница 4: ...r the burner from your supplier Please be sure that the front door burner door for the boiler is strictly closed and burner connections are properly made as the boiler is working GENERAL CHARACTERISTI...

Страница 5: ...OM SERIES CAST IRON BOILER TECNICAL DATA I...

Страница 6: ...OM SERIES CAST IRON BOILER TECNICAL DATA II...

Страница 7: ...OM SERIES CAST IRON BOILER DIMENSIONS BOILER ROOM SETTINGS AND BOILER PLATFORM DIMENSIONS 11 A W B C D E...

Страница 8: ...ary This will prevent chalk and dust and the life of the ssytem will be long The water in the radiator or heating system is not healthy Do not use this water as drinking or cleaning water Do not take...

Страница 9: ...cel the related standards requirements The Meanings Of The Shortenings In Diagram KSD Bo ler Water Heat Sense Element KGS Boiler Leaving Water KDS Boiler Return Water ID Heating Cell KKPD Boiler Prote...

Страница 10: ...DIAGRAM OF A SAMPLE SINGLE BOILER HEATING CIRCUIT WITH WATER HEATER 16 OM SERIES CAST IRON BOILER...

Страница 11: ...Volume resistance m h mbar m h mbar OM 06 325 000 377 9 21 67 102 16 25 54 OM 07 385 000 447 7 25 67 147 19 25 80 OM 08 435 000 505 8 29 00 180 21 75 105 OM 09 485 000 564 0 32 33 160 24 25 78 OM 10 5...

Страница 12: ...on pipes must be isolated Fuel tank must be positioned in higher level than the burner the height difference between the burner and fuel tank H must be more than 4 m In the seasons that the boiler is...

Страница 13: ...BOILER CONTROL PANELS Standard Boiler Control Panel Single Level Standard Boiler Control Panel Dual Level 20...

Страница 14: ...AGRAMS Standard Boiler Control Panel Single Level Electric Diagram Electric feedings is 220 V 50 Hz Monophase Standard Boiler Control Panel Dual Level Electric Diagram Electric feedings is 220 V 50 Hz...

Страница 15: ...be fixed as soon as possible Plumbing system must be made by certificated professionals under the terms of EN standards EN approved materials must be used in the system Fuel And Electrical Connections...

Страница 16: ...must be taken from every radiator Water must be in quality which mentioned on Page 12 plumbing instructions Boiler must not be filled up with water when it is hot This can cause cracks in sections INS...

Страница 17: ...OM SERIE CAST IRON BODY BOILER CABIN PARTS LIST Safety valve and expansion tank must be connected directly to the boiler and the place of use without using any valve between 25 IMPORTANT...

Страница 18: ...26 0 30 1 20 2 70 3 30 3 90 4 50 2 10 100 200 300 400 500 600 800 700 100 130 180 200 220 160 10 20 30 40 50 60 80 70 90 100 900 5 10 5 70...

Страница 19: ...ater line must be arranged near the boiler And for filling out the water of the boiler in necesarry conditions there must be a connection to drainage in the system If there are any electric keys cable...

Страница 20: ...ems or failure boiler must not be started Water level of the boiler must be controlled Water must be added to the boiler if the water level is low Please call technicians if there is a water leakage L...

Страница 21: ...fety thermostate switch after the boiler is cold enough Burner must start If the boiler doesn t start or if the safety thermostat stop the boiler again please call technical services If the burner saf...

Страница 22: ...oof of the connections of the boiler test Valves tests for proper opening and closing Fuel filter test cleaning if needed Sensor of the burner liquids tests Cleaning or renewing If needed Working and...

Страница 23: ...that isolate front door with front section and flue with back section must be controlled and must be renewed if needed BURNER DOOR AND BURNER CONNECTION Burner Door In burner connection process there...

Страница 24: ...ect proper burner must be chosen according to gas to gas side resistance valu es of the boiler Our company is not responsible for any possible problem if not certificated or out of standard burner is...

Отзывы: