SUN2000-(25KTL, 30KTL)-US
User Manual
6 System Operation
Issue 03 (2017-04-01)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
80
6
System Operation
6.1 Powering On the SUN2000
Power on the SUN2000 after electrical connections are completed.
Procedure
Step 1
Turn on the AC switch between the SUN2000 and the power grid.
If you perform
Step 2
before
Step 1
, the SUN2000 reports a fault about abnormal shutdown.
You can start the SUN2000 only after the fault is automatically rectified. The default
clearance time is 1 minute. You can modify the time over the network management software
running on a PC connected to the SUN2000.
Step 2
Press
DC SWITCH
at the bottom of the inverter and rotate it to the
ON
position.
Step 3
(Optional) To check whether the DC terminal is securely connected, after the SUN2000
works for some time, measure the temperature at the DC terminal connection point using a
point-test thermometer.
After the inverter has been running for a period, measure the temperatures at the joints
between DC terminals and connectors to check that the DC terminals are in good contact.
----End
6.2 Powering Off the SUN2000
Comply with the safety precautions and operation procedure specified in this section when
powering off the SUN2000.
Context