Hardware options installation 72
15.
Install hot-plug drives.
CAUTION:
To prevent improper cooling and thermal damage, do not operate the server unless
all bays are populated with either a component or a blank.
Populate drive bays based on the drive numbering sequence. Start from the drive bay with the lowest
device number. For device numbering information see "SAS and SATA device numbers (on page
15
)."
16.
Install the fan modules and the fan blank (on page
31
).
17.
Install any full-length PCI expansion cards that were removed ("
Installing an expansion board
" on page
63
).
18.
Install the system air baffle (on page
28
).
19.
If removed, install the PCI air baffle ("
PCI air baffle option
" on page
38
).
20.
Install the access panel (on page
26
).
21.
Return the server to an upright position.
22.
Install the front bezel (on page
25
).
23.
Connect each power cord to the server.
24.
Connect each power cord to the power source.
25.
Power up the server (on page
23
).
Redundant hot-plug power supply enablement kit
option
To install the component:
1.
Power down the server (on page
23
).
2.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
3.
Unlock the front bezel (on page
24
).
4.
Place the server on its side.
Содержание ProLiant ML350e Gen8
Страница 16: ...Component identification 16 LFF drive numbering Four bay four bay LFF drive numbering hot plug only ...
Страница 90: ...Cabling 90 RPS configuration Integrated configuration showing Smart Array controller card installed ...
Страница 91: ...Cabling 91 RPS configuration showing Smart Array controller card installed ...
Страница 119: ...Support and other resources 119 ...
Страница 120: ...Support and other resources 120 ...