4 210 256 / 01
5
Assembly
1.4 Guarantee
Trouble-free functionality is only guaranteed when
both these and the operating instructions are meticu-
lously observed and the boiler is regularly serviced
by a qualified engineer (maintenance contract). Re-
pair of faults and damage caused by contaminated
operating materials (gas, water, combustion air),
unsuitable chemical additives in the heating water,
careless treatment, faulty installation, unauthorised
modifications and damage as a result of force are
not subject to our guarantee liability; this applies also
to corrosion caused by halides, e.g. emanating from
spray canisters, paints and varnishes, adhesives,
solvents and cleaning agents.
2. Assembly
2.1 Installation, levelling
The boiler is fixed to wooden transport chocks. For
transport up and down stairs, it is wise to leave these
timbers in place under the boiler.
A special foundation plate for the boiler is not an es-
sential, but it is recommended.
Space required
The flange of the boiler must be able to be swung out
fully, with burner installed (see chapter 3.4).
Installation of the boiler
1. Unbolt the boiler from the wooden pallet and
remove the transport securing devices.
2. Levelling the base:
The base must be levelled both lengthways and
crossways with a spirit level. This is carried out
by adjusting the nuts on the boiler feet. After this
adjustment, the upper (locking) nuts on the boiler
feet must be tightened thoroughly.
2.2 Assembly of the condensate dis-
charge and neutralisation box
For the condensate discharge, there a four versions
available. The assembly is carried out, according to the
version supplied, in accordance with the illustrations.
The condensate discharge must be
fabricated of corrosion resistant ma-
terial (see chapter 4.7).
Содержание UltraOil 50
Страница 27: ...4 210 256 01 27 Maintenance 2 8 9 7 1 4 10 Fig 14 6 5 3...
Страница 43: ...4 210 256 01 43...