Operation
HORIBA
18/ 24
NOx Converter Checker CC-100E
Switch off gas supply
1.
Stop the ozone production by pressing the "OGU" button and then "OFF".
2.
Close the SV3 valve and stop the NO supply.
3.
Start a flushing process with nitrogen for at least one minute. To do this, open valve SV2 for the N2
supply.
4.
Close the SV1 valve and stop the O2 supply.
5.
Close the SV2 valve and finish the flushing process.
6.
Switch off the unit at the mains switch.