Installation and commissioning
NOx Converter Checker CC-100E
13/ 24
4.2 Environmental conditions
The unit is designed for the following environmental conditions.
–
Overvoltage category: II
–
Pollution degree: 2
–
EMC: EN61326-1: 2013-07 Class A, Industrial
–
Mains connection: AC 90 V to 240 V, 50/60 Hz
–
Gas pressure: 20 kPa (200 mbar)
–
Operating temperature: 5 °C to 35 °C
–
Rel. humidity: < 80 %, non-condensing
–
No direct exposure to heat and sunlight
4.3 Installation
WARNING
Hot surfaces on the appliance, risk of burns
During operation, the surface of the appliance becomes hot.
a)
Do not touch the surface during operation.
b)
Allow the unit to cool down before starting installation or maintenance work.
Connect
Fig. 5:
Rear view
Place the unit on a level, stable surface.
1.
Connect the gas supply lines (1 to 3).
2.
Connect the bypass line (7) to a venting system.
3.
Connect the "Analyser" output (4) of the CC-100E to the gas input of your analyser.
4.
Make sure that all screw connections and lines are connected gas-tight before using the system for the
first time.
5.
Set the correct inlet pressure according to the specification.
6.
Connect the mains cable.
7.
Switch on the unit.
8.
The HORIBA start screen appears.
9.
Operate the function via touch screen.