Transport, installation and start‐up
User manual for HON R100 gas pressure regulator with HON P095NG pilot
35
Conduct a final inspection to check whether the following criteria are met:
All screwed connections on the device and supply lines are securely fastened.
If …
then …
at least one criterion is not met,
you should correct the error before proceeding
with the next task.
all criteria are met,
you may proceed with the next task.
Proceed as follows:
Installing the device connections
(see page 35)
5.3
Installing the device connections
Some of the measuring impulse lines will come pre‐installed:
Figure
No.
Designation,
category,
installation condition
Front:
Back:
1
Motorization line
Operating line
pre‐installed
2
Outlet pressure measuring line
Operating line
needs to be installed
3
Outlet pressure discharging line
Operating line
needs to be installed
4
Inlet pressure line
Operating line
needs to be installed
5
Outlet pressure feedback line
Operating line
needs to be installed
6
Outlet pressure line
Operating line
needs to be installed
Prepare the following materials:
Pipes, connecting pieces, and fittings as per the specifications in the
Technical specifica‐
tions
(see page 17)
Shut‐off devices for the operating and measuring lines, as well as other accessories, as
required, as per the
Basics for installing the device in a pipe
(see page 25) section.
The installation of the operating and measuring lines depends on the local conditions and the
gas regulating line in which the gas pressure regulator is being used. Please refer to the
Basics
for installing the device in a pipe
(see page 25) section for more information on what needs to
be ensured without fail in the corresponding design and implementation.
Final inspection
Next task
Operating and measuring
lines that are
pre‐installed and that
need to be installed
Preparing the materials
Installing the operating
and measuring lines