AdaptaPAK® Installation
Startup Procedures
As with other aspects of installing a system, following proper startup procedures is of critical importance to the
eventual safe and effective operation of the system. Although unique characteristics of every installation may
require some variation, the following procedures should be followed as closely as possible. All refrigeration startups
should be performed by a qualified refrigeration technician.
Startup Checklists
An essential part of any startup is the careful and detailed verification of the necessary steps needed to get the
system operating. Verification, therefore, should be documented during the process to ensure adherence to all
quality and performance standards listed below, as well as, any that might be provided by the customer.
Typically the steps in the startup process include:
•
Pressure testing
•
Evacuating the piping
•
Adding oil
•
Adding refrigerant
•
Installing liquid line driers and suction filters
Whether customers provide one or not, a startup checklist like the one included here (beginning on next page)
should always be used. The checklist provides space for two types of entries, information to be filled in, and items to
be checked off. Unless an item is not applicable to the installation, all items should be filled in or checked off.
SYSTEMS START-UP CHECK LIST
CUSTOMER NAME: _________________________ DATE: ______
UNIT MODEL #: ______________________________________
UNIT SERIAL #: _______________________________________
1. Verify that all electrical connects have been made and properly tightened. _____
2. Verify the Main Power Voltage readings and phasing of voltage against equipment requirements prior to turning on
the power source:
L 1 > GD ______________ A > B ______________
L 2 > GD ______________ A > C ______________
L 3 > GD ______________ B > C ______________
3. Verify the Control Voltage. _____
4. On condensers check for proper operation and fan rotation including split valve operation and pump-out
solenoids. _____
Содержание Adaptapak ADP-M0000-L0032
Страница 4: ...4 AdaptaPAK Parallel Refrigeration System ...
Страница 20: ...20 AdaptaPAK Parallel Refrigeration System ...
Страница 26: ...26 multiMAX Controller for AdaptaPAK Hillphoenix AdaptaPAK multiMAX Controller Input Output Schedule left side ...
Страница 28: ...28 multiMAX Controller for AdaptaPAK ...
Страница 66: ......