Installation Manual
Version 1.1
8
Part Number MAN-000014
Repeat Steps 1
– 13 for all bin legs. After completing steps 1-13 for each leg (and
before continuing to step 14), re-examine each leg to ensure proper clearances as
noted and adjust as needed.
Anchor the Bin
14.
Drill two anchor bolt holes 2 1/4” deep in the pad diagonally
opposite of each other. (
Figure 6
)
When anchoring 15K or greater assemblies you
will use four (4) anchor bolts.
15. Hammer bolts into cement until they are firmly in place.
16. Tighten the nuts of the anchor bolts using a socket or hammer drill to
anchor the bracket assembly. Torque to 55 ft.-lbs.
17. Drop retention clip into place over bolt as shown in
Figure 7
.
Figure 6: Drill anchor bolts 2 1/4" deep.
Figure 4: Lift until there is a 1/2" (+/-
1/8”) gap.
Figure 5: Leave
1/4” (+/- 1/8”) gap between C-
channel and bracket.
Figure 7: Retention clip (shaded) over bolt