6. Installation

6.1 General

After reading the previous sections in this booklet and 
choosing a good location for the unit please install, 
paying attention to the following hydraulic, electrical 
and commissioning sections.

Boiler selection

 

`

The boiler should have a control thermostat 
and non self-resetting thermal cut-out and be 
compatible with unvented storage water heaters.

 

`

Can be a sealed system or open vented type - 
maximum primary pressure 3 bar.

 

`

The primary flow from the boiler must be pumped. 
Gravity circulation will not work due to the 
special design of the primary heat exchanger. It is 
recomended that an air bleed point or automatic 
air vent is incorporated in the primary return 
pipework close to the unvented system.

 

`

The boiler cannot be vented through the cylinder.

Limitations
The cylinder should not be used in association with any 
of the following:

 

`

Solid fuel boilers or any other boiler in which the 
energy input is not under effective thermostatic 
control, unless additional and appropriate safety 
measures are installed.

 

`

Ascending spray type bidets or any other class 1 
back syphonage risk requiring that a type A air gap 
be employed.

 

`

Steam heating plants unless additional and 
appropriate safety devices are installed.

 

`

Situations where maintenance is likely to be 
neglected or safety devices tampered with.

 

`

Water supplies that have either inadequate 
pressure or where the supply may be intermittent.

 

`

Situations where it is not possible to safely pipe 
away any discharge from the safety valves.

 

`

In areas where the water consistently contains a 
high proportion of solids, e.g. suspended matter 
that could block the strainer,  unless adequate 
filtration can be ensured.

 

`

In areas where the water supply contains chloride 
levels that exceed 250mg/l.

5.3 Choice of location

The cylinder must be vertically floor mounted. Although 
location is not critical, the following points should be 
considered:

 

`

The cylinder should be sited to ensure minimum 
dead leg distances, particularly to the point of 
most frequent use.

 

`

Avoid siting where extreme cold temperatures will 
be experienced. All exposed pipe work should be 
insulated.

 

`

The discharge pipework from the safety valves 
must have minimum fall of 1:200 from the unit and 
terminate in a safe and visible position.

 

`

Access to associated controls and immersion 
heaters must be available for the servicing and 
maintenance of the system. Where these controls 
are installed against a wall a minimum distance of 
250mm must be left.

 

`

Ensure that the floor area for the cylinder is level 
and capable of permanently supporting the weight 
when full of water (see table 1 & 3, page 5 & 6 for 
weights).

 

`

Prior to installation the unit should be stored and 
transported in an area free from excessive damp or 
humidity.  The Unit should be stored in a frost free 
environment.

WALL

Min 250mm

Min 250mm

Figure 6: Acess schematic (not to scale)

Содержание PremierPlus

Страница 1: ...PremierPlus Unvented Hot Water Cylinder Installation and User Manual...

Страница 2: ...ntenance operations 21 10 Troubleshooting 22 10 1 Fault finding 22 11 Decommissioning 23 11 1 Decommissioning procedure 23 12 1 Spare parts list 23 Benchmark checklist 25 Commissioning service records...

Страница 3: ...appliance Faulty or insufficient maintenance of the appliance Failure to abide by the instructions on installing the product Installer s liability The installer is responsible for the installation and...

Страница 4: ...and the mains water supply Do not switch on if there is a possibility that the water in the cylinder is frozen DANGER This cylinder is unvented and as such becomes pressurisedwheninoperation Thecombin...

Страница 5: ...ssure 1 6MPa 16 bar Max design pressure 0 8MPa 8 bar Max operating pressure PRV 0 35MPa 3 5 bar Expansion relief valve setting 0 6MPa 6 bar T P valve setting 1 0MPa 10 bar 90 C Maximum primary pressur...

Страница 6: ...199 246 295 295 355 355 Weight empty kg 23 25 28 29 36 45 45 55 55 Max supply pressure 1 6MPa 16 bar Max design pressure 0 8MPa 8 bar Max operating pressure PRV 0 35MPa 3 5 bar Max expansion vessel c...

Страница 7: ...170E 210E 250E 300E B 306 306 306 306 306 306 306 C 493 616 800 925 1184 1437 1751 D 784 906 1090 1216 1474 1726 2040 Item 100B 120B 150B 170B 210B 250B 300B A 315 315 315 315 315 315 315 B 354 354 35...

Страница 8: ...s with controls selected A double pole isolating switch must be installed in the mains supply All earth connections must be connected back to the mains earth supply 3 DHW OFF 2 3 L 1 N 2 3 HTG ON DHW...

Страница 9: ...3 Control Housing Details Element Connections 1 5mm 3 Core HOFR sheathed cable Indirect control wiring N L 1 5mm 3 Core HOFR sheathed cable Figure 5 Direct wiring schematic Figure 4 Indirect wiring s...

Страница 10: ...ions as listed below Building Regulations G3 The Building Standards Scotland The Building Regulations Northern Ireland I E E Electrical Regs UK Water Regulations 5 1 Installation regulations 5 2 Insta...

Страница 11: ...r supplies that have either inadequate pressure or where the supply may be intermittent Situations where it is not possible to safely pipe away any discharge from the safety valves In areas where the...

Страница 12: ...connection if required Cold water combination valve Mains water supply Isolating valve not supplied Discharge pipe Tundish Drain cock not supplied Secondary return if required use swept tee Inlet NOTE...

Страница 13: ...d with the discharge pipework in either the horizontal position or facing downwards Where discharge pipework is difficult to attain the local building control officer from the local council should be...

Страница 14: ...onze circulation pump will be required On large systems due to the increase in system water content it may be necessary to fit an additional expansion vessel to the secondary circuit This should be do...

Страница 15: ...nd lower than the valve with no more than 600mm of pipe between the valve outlet and the tundish see fig 10 Note To comply with the Water Supply Water Fittings Regulations the tundish should incorpora...

Страница 16: ...e continuously marked with a warning that no sanitary appliances should be connected to the pipe Note 1 Plastic pipes should be joined and assembled with fittings appropriate to the circumstances in w...

Страница 17: ...p to 27m 1 4m 1 7m 2 3m Table 5 Sizing of copper discharge pipe D2 for common temperature relief valve outlet sizes Safety device e g Temperature relief valve Metal discharge pipe D1 from Temperature...

Страница 18: ...e unit within the central heating system Other controls will be necessary to control the space heating requirements and times that the system is required to function The cylinder is compatible with mo...

Страница 19: ...hermostat s and that no water has discharged from the expansion relief valve or temperature pressure relief valve during the heating cycle Indirect units Fill the indirect primary circuit following th...

Страница 20: ...direct units immersion heater s All immersion heaters are fitted with a combined thermostat and thermal cut out located under the terminal cover mounted on the side of the product Access to the therm...

Страница 21: ...ply and turn off boiler Attachahosepipetothedraincockhavingsufficient length to take water to a suitable discharge point below the level of the unit Open a hot tap close to the unit and open drain coc...

Страница 22: ...rect thermostat Indirect motorised valve not connected correctly Check wiring and or plumbing connections to motorised valve Water discharges from expansion valve Intermittently Expansion vessel charg...

Страница 23: ...Pressure reducing valve cartridge 3 5 bar 95605898 11 Temperature Pressure Relief Valve 95605810 12 Expansion vessel 12 litre 100 120 and 150 litre models not shown 95607863 13 Expansion vessel 18 lit...

Страница 24: ...ure 12 Exploded view of cold water combination valve Cold Mains Connection 22mm Outlet Connection 22mm Outlet Connection 15mm 9 10 7 8 4 3 17 11 20 17 18 1 19 3 4 2 22 22 23 Figure 13 Cylinder explode...

Страница 25: ...set temperature C I min Yes Type of control system if applicable Y Plan S Plan Other Is the cylinder solar or other renewable compatible Yes No What is the hot water temperature at the nearest outlet...

Страница 26: ...Telephone No Comments Signature SERVICE 07 Date Engineer name Company name Telephone No Comments Signature SERVICE 09 Date Engineer name Company name Telephone No Comments Signature SERVICE 02 Date E...

Страница 27: ...subjected to frost nor has it been tampered with or been subject to misuse or neglect No factory fitted parts have been removed for un authorised repair or replacement The Benchmark commisioning chec...

Страница 28: ...te responsibility and sustainability charters and reduce our printed material we encourage you to download product brochures from our website In designing these files we have taken into account the ne...

Отзывы: