44
M
AINTENANCE
AND
S
ERVICING
Note
Turn clockwise to decrease temperature.
Turn counterclockwise to increase
temperature.
Warning
Shock Hazard: Unplug power cord
before performing these procedures.
Figure 25: Thermostat (EC5500)
Figure 26: Overtemp Switch
3.
Locate thermostat: EC5500 — Remove top
cover (see Figure 25). EC6000 — On the back
of the unit, remove the 1-1/4” cover located in
the bottom center of the back.
4.
Loosen the locking screw on the thermostat (see
Figure 25).
5.
Turn the temperature adjustment screw to either
increase or decrease temperature.
6.
Tighten the locking screw on the thermostat.
7.
Repeat steps 1/8 under “Chamber Temperature.”
8.
Repeat procedure until the temperature falls
within the 265
°
F - 275
°
F range.
9.
Replace covers.
Thermostat Replacement
1.
Verify the chamber pressure is 0 PSI and the
unit is at room temperature.
2.
Disconnect from power source and remove top
cover.
3.
Disconnect wire leads (see Figure 25).
4.
Remove the thermostat from its socket. To do
this, loosen set screw holding the thermostat in
place.
5.
Install the replacement thermostat. Align the key
in the slot of the socket and tighten set screw.
6.
Reconnect the wires.
7.
Test and adjust thermostat according to “Cham-
ber Temperature” procedure and “Thermostat
Adjustment.”
Overtemp Switch
Functional Check and Replacement
1.
Unplug unit from the power source.
2.
Remove the top cover.
3.
Disconnect wires from the over temp switch.
4.
Test continuity of the over temp switch. If the
switch is open, reset by pushing center button. If
the switch will not reset, replace it.
5.
Remove the hardware that secures the switch to
the chamber.
6.
Install the replacement switch.
7.
Reconnect the wire leads and replace cover.
Overtemp
Switch
Chamber
Heater
Содержание Chemiclave EC5500
Страница 15: ...15 Figure 4 Metering Valve Function PRINCIPLES OF OPERATION ...
Страница 16: ...16 Figure 7 Pressurization PRINCIPLES OF OPERATION Figure 6 Ready Load Figure 5 Warm Up ...
Страница 17: ...17 Figure 8 EC5500 EC6000 Operation PRINCIPLES OF OPERATION ...
Страница 18: ...18 Figure 11 End Unload Figure 10 Purge Figure 9 Exposure PRINCIPLES OF OPERATION ...
Страница 20: ...20 Figure 13 Piping Schematic PRINCIPLES OF OPERATION ...
Страница 21: ...21 Figure 14 Cycle Phase Diagram PRINCIPLES OF OPERATION ...
Страница 22: ...22 Door Gasket Figure 15 Exploded View Top Cover and Door PRINCIPLES OF OPERATION ...
Страница 32: ...32 MAINTENANCE AND SERVICING Figure 17 Metering Valve need new drawing ...
Страница 39: ...39 MAINTENANCE AND SERVICING Figure 22 Power Supply Printed Circuit Board ...
Страница 56: ...56 ...