 Assembly instructions terrace awning TR850

D.   Fitting instructions Terrace awning

The terrace awning is a sunblind which must 
be fitted perfectly square and vertical. The 
guide rails must be set up absolutely parallel 
to one another. It is very important to work 
with extreme accuracy and to make sure that 
the base supports are solidly secured.
Where it is not possible to assemble on a 
good concrete surface, it is advisable to lay 
a foundation. We recommend a size of  30 x 
30 x 60 cm for the concrete blocks. If desired, 
light reinforcement may be included to pre-
vent the concrete from cracking (fig. 1).

If the differences in level are such that they 
cannot be evened out, this must be stated 
on your order form. The highest point of 
the floor will then be taken as the reference 
height for all other measurements.

The difference in level can be determined 
precisely by using a water hose.

A spirit level is insufficiently pre-
cise in most cases to determine 
levels (fig. 2).

A. Assembling the casing

The casing is secured to the wall 
at each end by hinge pieces. Mark 
the drilling holes on the walls. 
Check the exact distance between 
the fixing points. Proceed as 
follows:
-  First mark out the width of the 

casing

-  Then move in 41 mm form each end and mark a vertical line using a spirit level
-  Then mark the desired height on this line so that the top edge of the casing matches the measure-

ment given on the order.

-  As a check, measure the external dimension of the casing with respect to the floor using a plumb line.
-  Draw a line on the ground at the required distance, perpendicular to the wall. The ground plates 

for the base supports will fit inside this line in all cases. If necessary, calculate the squareness using 
Pythagoras’rule: a² = b² + c² (see fig. “). The square- ness of this line is very important, and will guaran-
tee that the fabric rolls up properly in the future.  

    If all measurements are correct and there is sufficient room to set up the base supports, you can start 

drilling the final holes for the wall fixings. The holes should be drilled using a 16 mm drill. Then insert 

fig. 1: Foundation

concrete floor

floor tilling

foundation 30x30x60

40 cm

fig. 2: Difference in level

niveauverschil

level

extension

B

h

H

Содержание TR850

Страница 1: ...Assembly instructions Terrace awning TR850 art nr 6837...

Страница 2: ...r apprentice fitters Before you start please do read these instructions thoroughly The tightening of springs creates important powers Be very careful and make sure of a solid footing whilst operating...

Страница 3: ...The casing is secured to the wall at each end by hinge pieces Mark the drilling holes on the walls Check the exact distance between the fixing points Proceed as follows First mark out the width of the...

Страница 4: ...h the casing fig 5 2 For mounting on the ceiling a mounting clip can be added if necessary 3 For walls in poor condition it is recom mended to select the most suitable fixings for each individual case...

Страница 5: ...of the guide rail over the internal pulley fig 8A Let the fabric bar exit at the other end of the rail B Slip the end of the cable B through the opening in the fabric bar Now pull the cable forwards...

Страница 6: ...can no longer be pulled out of the rail Drill a hole through the guide rail in to the pin of the cover in the position indicated and fix the cover with a parker screw fig 7 Now remove from the packagi...

Страница 7: ...these must be kept even and the position of the rollers must be identical at left and right Now take a spirit level and a ruler and position the base supports perfectly vertical and at their correct d...

Страница 8: ...erly throughout Then hook the left hand plate with a pulley to the springs Fasten the claw of the cable tensioning device around the plate Set the springs to tension fig 19 Pull using the cable tensio...

Страница 9: ...places over the spring as a temporary measure Leave these pieces of clip section in place temporarily during adjustment of the blind In this way it is very easy to check the position of the spring and...

Страница 10: ...s used must be in accordance with the existing norms and requirements Connecting the single pole switch and adjusting the motor Connect the motor with a test cable first E 1 Single pole switch Connect...

Страница 11: ...itself Let the awning unroll until you have reached the desired end position Turn the switch of the test cable into its zero position Now you push the white or the yellow button on the motor head dep...

Страница 12: ...is desired to operate the sun blind using a single switch it is necessary to use a relay box If this is not done the system will oscillate and the high inductive and capacitative voltages created will...

Страница 13: ...ils immediately below the corner To prevent sideways movement of the guide rails measures must be taken to ensure lateral stability Try to make a connection to some other element which will provide la...

Страница 14: ...lt of the dirt which is always in the air the fabric and the rails will certainly become dirty after a certain time These particles of dirt may settle in the groove ahead of the runners Accumula tions...

Страница 15: ...e Faulty adjustment of limit switches see p 4 Internal flap not straight Guide rails are parallel but not square to the casing Check by applying Pythagoras rule 3 4 5 or measuring diagonals 5 Internal...

Страница 16: ......

Отзывы: