HAMWORTHY HEATING LTD
WESSEX 100 M
500001080/F
iii
PAGE
9.0 ELECTRICAL SUPPLY
...................................................................................................................
11
9.1 Site Wiring
9.2 Indication Signals and Volt Free Contacts
9.3 Milton Boiler Sequence Control and Sequencing Interface Module (Optional)
10.0 BOILER ASSEMBLY AND INSTALLATION
..................................................................................
14
10.1 General
10.2 Connection of Boilers to the Flue System
10.3 Water Connections
11.0 COMMISSIONING AND TESTING
.................................................................................................
15
11.1 Electrical Installation
11.2 Gas Installation
11.3 Water Circulation System
11.4 Commissioning the Boiler
11.4.1 Boiler Checks Prior to Lighting
11.4.2 Procedure for Initial Lighting
11.4.3 Checking/Adjusting Inlet and Setting Pressures
11.4.4 Combustion Check
11.4.5 Air Inlet Damper
11.4.6 Safety Checks
11.5 External Controls
11.6 Installation Noise
11.7 User’s Instructions
12.0 FAULT FINDING
.............................................................................................................................
19
12.1 Safety Features Summary
12.2 Fault Finding Procedures
12.3 Possible Causes of Boiler Lockout
13.0 SERVICING
.....................................................................................................................................
20
14.0 REPLACEMENT OF FAILED COMPONENTS
...............................................................................
24
15.0 RECOMMENDED SPARES
............................................................................................................
29
APPENDIX ‘A’ - INFORMATION RELATING TO PROPANE FIRING
...............................................................
30
APPENDIX ‘B’ - CONTROL THERMOSTAT SETTING PROCEDURE
..............................................................
31
Содержание Wessex 100 M100
Страница 39: ...Notes ...