P/N G610B
April, 2016 (Rev 0)
Page 10
SYSTEM INSTALLATION INSTRUCTIONS (Cont'd)
AIMING THE SPRAY NOZZLES
14. Determine the height between the top of the
cooking surface and the top of the distribution
assembly housing. It must be between 16 inches
and 27 inches.
(See
FIGURE 5
)
15. Loosen the two clamp nuts using the 11/32” Nut
Driver. Loosen the clamps just enough to be able
to adjust the nozzles, but leave enough pressure
that the nozzles will stay in the position you rotate
them too.
Make certain that the nozzle
assembly does not slide left or right in the
housing during adjustment or the housing
cover will not fit properly. The Nozzle
Assembly must be centered in the housing
for proper fit of the housing cover over the
nozzles.
16. Using the Nozzle Aiming Gauge provided, adjust
the nozzles to the correct angle based on the
height determined in step 14. This is done by
placing the Gauge in the housing and aligning the
nozzles spray hole with the corresponding
height/angle on the Gauge. Once in the correct
position tighten the clamp nuts to secure the
Nozzles in place
(See
Figure 9 & 10
. The
example in Figure 9 is set to 23 inches or 45.9
degrees.)
17. Place the gauge back in the housing to make
sure the nozzles are still at the correct angle; that
they did not shift during the tightening process.
18. Mount the cover on the Distribution Housing by
sliding the bottom of the cover into the housing
below the nozzles and then rotating the cover up
over the nozzles. Carefully install 4 self-tapping
screws through the top of the cover and into the
pre-drilled holes of the housing.
FIGURE 10
FIGURE 9
Clamp Nut
Nozzle Spray
Hole
Clamp
Mounting Post
Right Nozzle
Gauge
Left Nozzle
Gauge
Permit Number:
20-04649