30" - 36" Platform Assembly
19
PNEG-1295
16" - 36" Platforms
RIGHT HAND DRIVE SETUP
LEFT HAND DRIVE SETUP
Place vertical posts in position as shown below
in Figures 10-A & 10-B. Fasten with 3/8" x 1"
bolts and whiz nuts. Make sure not to tighten
hardware until assembly is complete. The
angle in the middle on the end sits on top of
Figure 10-A
Figure 10-B
1
Vertical Post, 47.5
(HSP30124)
2
Vertical Post, 41.375
(HSP30129)
1
Vertical Post, 47.5
(HSP30124)
1
Vertical Post, 47.5
(HSP30124)
1
Vertical Post, 47.5
(HSP30124)
2
Vertical Post, 41.375
(HSP30129)
1
Vertical Post, 47.5
(HSP30124)
1
Vertical Post, 47.5
(HSP30124)
Handrail Post
floor section on inside of the toeboards. All
the other angles fit on the outside of the
toeboards and flush with the bottom of the
support channels. When complete go back
and tighten hardware.
Содержание PNEG-1295
Страница 1: ...16 36 Platform Installation Manual PNEG 1295 PNEG 1295 Revision Date 10 16 2006...
Страница 2: ......
Страница 30: ...Rest Platform 30 PNEG 1295 16 36 Platforms REST PLATFORM ASSEMBLY...
Страница 39: ...Rest Platform 39 PNEG 1295 16 36 Platforms 14 Ladder Assembly at Rest Platform Figure 31...