Gossen Metrawatt GmbH
27
SECU
TEST ST
B
ASE
(
10
) /
P
RO
and SECU
LIFE ST
BASE
(25)
13.3 RPE – Protective Conductor Resis-
tance for Protection Category I DUTs
1
10/25 A RPE measurements are only possible with line
voltages of 115/230 V and line frequencies of 50/
60 Hz.
2
The selected offset value is permanently saved and used in mea-
surements performed in switch positions
A1 to A9
.
3
Connection also via EL1, VL2E, AT3 adapter, AT16DI/AT32DI
➭
Connect the DUT to the test socket.
➭
Contact all conductive parts which are
connected to the protective conductor
with test probe P1.
Special Case: Permanently Installed DUT
➭
Contact all conductive housing parts
with test probe P1.
Meas. Parameter
Meaning
Measurement type
Permissible test current IT
Passive: PE(TS) – P1
@ IT = 200 mA/10 A/
25 A
Testing is conducted between the two
protective conductor terminals: at the
test socket
3
and test probe P1.
Active: PE(TS)-P1
@ IP = 200 mA
Same as
PE(TS) – P1
, but with line
voltage to the test socket and continu-
ously rising DC test current (PRCDs)
PE(mains) – P1
Perm. connected DUTs
@ IT = 200 mA/10 A
Testing is conducted between the
ground terminal at the mains and
test probe P1.
PE(mains) - P1 clamp
@ IT = 10 A (see section 13.18)
P1 – P2
@ IT =
200 mA/10 A/25 A
Only test instruments with feature H01:
2-pole measurement between test
probes 1 and 2 (see section 13.17)
IT(set)
It
200 mA
Test current: 200 mA AC (+/–/
DC)
10 A
1
10 A test current (feature G01)
25 A
1
25 A test current (feature G02)
f – only at 200 mA ~ (AC)
50 ... 200 Hz
Test frequency (adjustable in steps)
Offset
> 0 ... < 5
2
Zero balancing for a selected ref-
erence point.
Select measuring function
1
R
PE
Select parameters
2
Set parameters
3
Connect the DUT
4
PE(TS) – P1
P1
PE(mains) – P1
PE(mains)
P1
Start test
5
Acknowledge line voltage warning
6
!
Only when active: PE(TS)-P1
Save measured values to clipboard
6
Stop test
7
Save measurements under ID no.