- 45A SIL 3 NC contact Relay Out Module for NE or F&G/ND Load with full diagnostic and Modbus 

G.M. International ISM0222-9 

Ordering information 

Front Panel and Features 



SIL 3 according to IEC 61508:2010 Ed. 2 with Tproof = 7 / 20 yrs (

10% / >10 % of total SIF) for NE Load, 

PFDavg (1 year) 1.391 E-05, SFF 97.81% . 



SIL 3 according to IEC 61508:2010 Ed. 2 with Tproof = 11 / 20 yrs (

10% / >10 % of total SIF) for F&G/ND Load, 

PFDavg (1 year) 8.47 E-06, SFF 99.20% . 



SIL 2 according to IEC 61508:2010 Ed. 2 (Route 2H) with Tproof = 4 / 8 years (

10% / >10 % of total SIF), 

PFDavg(1year) 2.24E-04, DC 76.09%, SFF 86.49% for diagnostic with fault relay NO contact. 



SC 3: Systematic Capability SIL 3. 



Installation in Zone 2 / Division 2. 



Compatible with DCS/PLC pulse testing. 



Internal relay coil short circuit detection. 



Line and Load short/open circuit detection. 



The fault in the field is directly mirrored to the PLC DO. 



Solenoid resistance measurement even in presence of serial connected diodes (patented resistance measuring technique). 



RMS voltage (before and after load energization) and load current measurement . 



Automatic acquisition of voltage, current and load resistance values. 



Earth leakage detection on both ac phases in de-energized load condition. 



5 A high availability SIL 3 contacts for NE or F&G/ND load. 



6 A inrush current at 24 Vdc / 250 Vac. 



Input/Output/Supply isolation. 



EMC Compatibility to EN61000-6-2, EN61000-6-4, EN61326-1, EN61326-3-1 for safety system. 



ATEX, IECEx, UL & C-UL, UKR TR n. 898, TÜV Certifications. 



FM, FMC, EAC-EX Certifications (pending). 



TÜV Functional Safety Certification. 



Simplified installation using standard DIN-Rail and plug-in terminal blocks, with or without Power Bus, or customized Termination Boards. 

 

 

Model:  

D5295S 

Power Bus and DIN-Rail accessories: 
Connector JDFT050 

 

Cover and fix MCHP196 

Terminal block male MOR017 

Terminal block female MOR022 

Operating parameters are programmable from PC by the GM Pocket Portable Adapter 
PPC5092 via USB serial line and SWC5090 Configurator software. 

Terminal block connections 

4 3 2 1 

8 7 6 5 

12 11  10  9 

13 14 15 16 

21 22 23 24 

(SIL 3) + Output NE Load or F&G/ND Load 

SAFE AREA 

(SIL 3) - Output NE Load or F&G/ND Load 

+ Load Power DC/AC 

13

 

14

 

15

 

+ Input 

1

 

- Input 

2

 

(SIL 2) Fault Output 1 (30 V, 500 mA)  

3

 

(SIL 2) Fault Output 1 (30 V, 500 mA)  

4

 

- Load Power DC/AC 

16

 

Earth 

Not used 

Not used 

21

 

22

 

23

 

A-  Modbus Input/Output RS485 

5

 

B+  Modbus Input/Output RS485 

6

 

(Optional external resistor) 

7

 

(Optional external resistor) 

8

 

Not used 

24

 

+ Power Supply 24 Vdc 

9

 

- Power Supply 24 Vdc 

10

 

(SIL 2) Fault Output 2 (250 V, 3 A) 

11

 

(SIL 2) Fault Output 2 (250 V, 3 A) 

12

 

Содержание D5295S

Страница 1: ...E or F G ND Load with full diagnostic and Modbus G M International ISM0222 9 5 A SIL 3 NC contact Relay Output Module for NE or F G ND Load with full diagnostic and Modbus DIN Rail Power Bus and Termination Board Model D5295S D5295S INSTRUCTION MANUAL ...

Страница 2: ... on 28 02 2014 valid for 20 years Mounting EN IEC60715 TH 35 DIN Rail with or without Power Bus or on customized Termination Board Weight about 235 g Connection by polarized plug in disconnect screw terminal blocks to accommodate terminations up to 2 5 mm2 Location installation in Safe Area Non Hazardous Locations or Zone 2 Group IIC T4 or Class I Division 2 Group A B C D T4 or Class I Zone 2 Grou...

Страница 3: ...ergized load condition 5 A high availability SIL 3 contacts for NE or F G ND load 6 A inrush current at 24 Vdc 250 Vac Input Output Supply isolation EMC Compatibility to EN61000 6 2 EN61000 6 4 EN61326 1 EN61326 3 1 for safety system ATEX IECEx UL C UL UKR TR n 898 TÜV Certifications FM FMC EAC EX Certifications pending TÜV Functional Safety Certification Simplified installation using standard DIN...

Страница 4: ...rotection fuse or similar chosen according to the relay breaking capacity diagram All relay contacts are shown in de energized position MODEL D5295S 15 16 13 Load Power DC AC 11 12 1 2 9 10 3 4 14 SIL 3 Out 21 Power and Fault Bus F Modbus RS485 for diagnostic A B Load and Line Diagnostic Supply 24 Vdc In Fault Out 2 250 V 3 A A B MODBUS IN OUT RS485 Fault Out 1 30 V 500 mA Termination board connec...

Страница 5: ...ith the effective operating environment of the specific installation Units must be protected against dirt dust extreme mechanical e g vibration impact and shock and thermal stress and casual contacts If enclosure needs to be cleaned use only a cloth lightly moistened by a mixture of detergent in water Electrostatic Hazard to avoid electrostatic hazard the enclosure of D5295S must be cleaned only w...

Страница 6: ...put cumulative fault when the driver is on Load Supply Voltage When checked the load supply voltage can activate the cumulative fault Coil Integrity When checked the short circuit of any coil can activate the cumulative fault Load OFF Resistance When checked the load OFF resistance can activate the cumulative fault Isolation Resistance When checked the load to earth isolation resistance can activa...

Страница 7: ...e Bit position 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Coil Integrity Load Current Load Voltage 0 Ok 1 Fault Each Modbus parameter is described by one 16 bit word 1 See command details on the right 2 Expressed in 100 mV 3 Expressed in mA 4 Expressed in Ω 5 Expressed in kΩ 6 0 OFF 1 ON 7 0 Fault 1 Ok 8 0 Fault mirror 1 Always OFF 2 Always ON 9 0 no inversion open fault for SIL application 1 inverted ...