7 Fusion Preparation
Operating instructions SG 160
14
If you entered uncontrolled in the programming operation, it is sufficient to wait
20 second without pressing any key. The controller will switch back itself and
shows the actual temperature.
7.3
Butt fusion preparation
The machine can be prepared for butt fusion in only a few steps.
Loosen the knurled-head screw. Pressure is now built up via spring tension.
The groove in both eccentric screws (in front and at the back) should be
horizontal and secured with the safety screw. The heating plate can be moved
axially
Attention
Attention
Eccentric screw
Содержание SG 160
Страница 56: ...11 Customer service Operating instructions SG 160 52...
Страница 57: ...Operating instructions SG 160 11 Customer service 53...
Страница 58: ......
Страница 59: ......