Commissioning
4
Commissioning
Before enabling operation of the control panel:
X
Ensure that all external components are completely assembled and connected.
X
Take changes into consideration that have resulted during the installation (e.g. larger batteries may be neces-
sary in case of a battery-buffered system voltage of the power module
PM
).
X
Ensure that the batteries have been charged for at least 8 hours before service readiness.
X
Check all the functions of the system carefully.
X
Do not carry out settings that may have to be carried out via USB with software (wind speed, latching or dead-
man, etc.) until the system has been installed completely.
The system configuration can be called up and stored or printed out with the software of the unit manufacturer
via USB at the control module
CM
(refer also to Chapter 10).
When the system is put into operation, all the green status displays of the modules flash for a max. of 3 minutes
while the system is being configured. All the green status displays must light up continuously after configuration.
Permanent flashing of the green status displays signals a fault with the control module
CM
.
X
Check the BUS connection between power module
PM
and control module
CM
.
X
Check the connection of the supply voltage at the power module
PM
.
5
Operation
5.1 General mode of operation
WARNING!
Danger to life from malfunctions in the event of fire, as the escape route can fill with smoke!
The system must function without faults.
X
Eliminate all faults immediately.
X
If the
yellow
fault display of the RWA button lights up, inform those responsible immediately.
System malfunctions must be remedied immediately.
X
Ensure that the system operator has been instructed at least in the modes of operation described below.
Manual triggering for alarm (EMERGENCY-OPEN)
X
Break the glass at the RWA button and press the alarm switch.
Manual opening and closing of the ventilation
X
Press the OPEN or CLOSE button on the ventilation button or ventilation control unit.
à
Pressing the switch briefly for approx. 1 second is sufficient for latching (no continuous contact).
à
In the case of dead-man operation the ventilation only closes as long as the push button is pressed.
The process can be stopped by pressing the OPEN and CLOSE switches simultaneously.
Automatic opening and closing (e.g. wind-rain control) overrides manual activation.
5.2 Ventilation mode
The service technician can set parameters for several functions using the MBZ300 configuration software.
Opening and closing windows
The windows are divided into ventilation groups. Each ventilator group has one or more vent switches which you
can use to open and close the windows of the ventilator group together.
It is possible to configure parallel connections and priority circuits.