Functional / Post Repair / Preventative Maintenance Checkout Procedures
184
T2100-ST1 Treadmill, 110V / T2100-ST2 Treadmill, 220V
2097937-002 Rev G
11 March 2019
Host Communication
8.
Perform the following to test the host device’s
communication with the treadmill.
a.
Attach the controller cable for the host system
to the T2100-ST Series treadmill.
b.
Power on the T2100-ST Series treadmill.
c.
Power on the host system.
d.
Adjust the treadmills speed and elevation from
the host system.
Expected Results: Elevation and speed can be
adjusted with the controlling device.
Pass/Fail
e.
Stop the treadmill from the host system.
Expected Results: Unit can be stopped with the
controlling device
Pass/Fail
Electrical Safety Checks
9.
Perform the following to test the electrical safety of
the treadmill.
a.
Conduct the tests described in “Electrical Safety
Tests” on page 38 and “Conducting Leakage
b.
Report the pass/fail status for each step
performed.
c.
Report the measured values.
Expected Results: All electrical safety tests pass.
Pass/Fail
Earth Leakage Current to Ground
limits
1.
Forward Polarity (L1, L2)
NC
_________μA
Pass/Fail
500μA
2.
Neutral (L2) open,
Forward Neutral Polarity
SFC
_________μA
Pass/Fail
500μA
3.
Ground open, Forward Polarity
SFC
_________μA
Pass/Fail
500μA
4.
Ground open, Reverse Polarity
SFC
_________μA
Pass/Fail
500μA
5.
Neutral (L2) open,
Reverse Polarity
SFC
_________μA
Pass/Fail
500μA
6.
Reverse Polarity (L2, L1)
NC
_________μA
Pass/Fail
500μA
Ground Continuity
Resistance
1.
AC mains power cord ground
prong to exposed metal surface
(ground lug)
N/A
________
mΩ
Pass/Fail
100
mΩ