background image

Customer Name:

PMI Name:

GON/SO Number:

Field Service Name:

Equipment:

Country/City or City/State:

Required site assessment milestones

Date of completion (dd/mm/yyyy)

1) Check site before Magnet Delivery

2) Check site before installation start

Place an "X" in either Y or N column

Site Ready Checks at Installation

Y

N

General Site Planning

Room dimensions, including ceiling height, for all Exam, Equipment/Technical & Control rooms meets GE specifications.

Ceiling support structure, if indicated on the GE drawing, is in the correct location and at the correct height according to the

of any GE supplied components. Overhead support Structure has been confirmed with customer/contractor to meet required
GE provided criteria.

Rooms that will contain equipment, including staging areas if applicable, are construction debris free. Precautions must be

taken to prevent debris from entering rooms containing equipment.

Finished ceiling is installed. If applicable ceiling tiles installed per PMI discretion.

Adequate delivery route from truck to final place of installation has been reviewed with all stakeholders, all
communications/notifications have occurred, arrangements have been made for special handling (rigging, elevator, fork lift,
etc.). All floors along delivery route will support weight of the equipment, temporary reinforcements arranged if needed.

System power & grounding (PDB/MDP) is available as per GE specifications, installed at point of final connection and ready to
use. Lock Out Tag Out is available.

System power and grounded audit has been scheduled to be completed during installation of equipment. (If Required) GEHC
PM to confirmed if needed.

Adequate room illumination installed and working.

Cable ways (floor/wall/ceiling/Access Flooring) are available for installation of GE cables and are of correct length and
diameter. Cable ways routes per GE Final drawings and cable access openings areas installed at a time determined by GEHC
PM. Surface floor duct can be installed at time of system installation.

HVAC systems Installed, and the site meets minimum environmental operational system requirements.

Network outlets installed and computer network available and working.

Hospital IT/connectivity contacts have been engaged and information has been added to Project management tool. (If
Required)

Floor levelness/flatness is measured and within tolerance, and there are no visible defects per GEHC specifications. Floor
Strength and thickness have been discussed with customer/contractor and they have confirmed GE requirements are met.

Customer supplied countertops where GE equipment will be installed are in place.

Specific for MR

RF Shield installed with possible exception of magnet entrance. RF Shield Effectivity and Ground Isolation Test needed. If GE
responsible for supplying RF shield, the RF shield Effectivity and Ground Isolation Test data is a Mandatory attachment into
MyProjects.

Power and connectivity is available for magnet monitoring.

Delivery route for He dewars & gradient coil cart to the scanning room is available.

Chilled water supply for Water Cooled Compressor or Air Cooled Compressor is ready and meets GE specifications.

Water drain available in the equipment room, if applicable.

Power for MR compressor & Chiller is available.

Ensure cryogen venting system is available for magnet connection.

Exhaust fan system is installed and operational per GE requirements.

Status of work

General comments

System can be delivered

PMI signature

Site ready for installation

FS signature: optional

GLOBAL SITE READINESS CHECKLIST (DI)

DOC1809666 Rev. 5

GENERAL SPECIFICATIONS

GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and
protective screens or derivatives not mentioned in the order.
The final study contains recommendations for the location of GE equipment and associated devices, electrical
wiring and room arrangements. When preparing the study, every effort has been made to consider every
aspect of the actual equipment expected to be installed.
The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for
the pre-installation work and electrical power supply are given according to the information noted during
on-site study and the wishes expressed by the customer.
The room dimensions used to create the equipment layout may originate from a previous layout and may not
be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to
lack of information.
Dimensions apply to finished surfaces of the room.
Actual configuration may differ from options presented in some typical views or tables.
If this set of final drawings has been approved by the customer, any subsequent modification of the site must
be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations
must be noted.

customer's responsibility to ensure that the site and final equipment placement complies with all applicable
local requirements.
All work required to install GE equipment must be carried out in compliance with the building regulations and
the safety standards of legal force in the country concerned.
These drawings are not to be used for actual construction purposes. The company cannot take responsibility
for any damage resulting therefrom.

CUSTOMER RESPONSIBILITIES

It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the

final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to
ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and

up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the
delivery and installation date.
Prior to installation, a structrual engineer of record must ensure that the floor and ceiling is designed in such a
way that the loads of the installed system can be securely borne and transferred. The layout of additional
structural elements, dimensioning and the selection of appropriate installation methods are the sole
responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the
ceiling, floor or walls are the customer's responsibility.

DISCLAIMER

THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.

DATE

NAME

SIGNATURE

Date

Rev

/24

EN-MRI-TYP-SIGNA_EXPLORER-WEB.DWG

A

03/Aug/2018

SIGNA EXPLORER /SIGNA CREATOR

Typical

C2 - Disclaimer - Site Readiness

02

Содержание SIGNA EXPLORER

Страница 1: ...mplete set of final issue drawing GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings however caused All dimensions are in millimeters unless otherwise spe...

Страница 2: ...licable Power for MR compressor Chiller is available Ensure cryogen venting system is available for magnet connection Exhaust fan system is installed and operational per GE requirements Status of work...

Страница 3: ...ned to the magnet room If not possible a barrier is recommended to prevent entry to the 5g field area 2 The spaces around above and below the magnet must be reviewed for effects of the 5g 3g 1g and 5g...

Страница 4: ...contingent on a 72 in corridor width C 26 Minimum opening for is 43 in w x 82 in h contingent on a 96 in corridor width C 27 Counter top for equipment provide grommeted openings as required to route c...

Страница 5: ...efine RF shield s inset according to provisions made by the RF Shield vendor Warning 5 Gauss line outside the Magnet room limits MAGNET ROOM CONTROL ROOM FRONT VIEW WITH MAGNETIC FIELD 6 4 3 2 1 1 3 1...

Страница 6: ...ency generators Commercial laundry equipment Food preparation area Water cooling equipment HVAC equipment Major mechanical equipment room Credit cards watches and clocks Air conditioning equipment Fue...

Страница 7: ...net cover is adjustable between 100 200mm 4 8 in D PP cover is adjustable between 300 400mm 11 8 15 7 in SYSTEM CABINET Top View PENETRATION PANEL Top View D D PENETRATION PANEL Front View Cut out cen...

Страница 8: ...0 4 in 401 15 79 in 750 29 52 in 700 27 56 in 377 14 84 in 330 12 98 in 208 8 19 in GLOBAL OPERATOR CABINET GOC Center of Gravity SCALE 1 10 TOP VIEW FRONT VIEW SIDE VIEW 300 11 8 in PENETRATION PANEL...

Страница 9: ...ravity GAS SUPPLY RETURN WATER OUT IN 232 9 13 in 450 17 72 in 103 4 06 in 276 10 87 in 153 6 02 in 450 17 72 in 800 31 5 in 153 6 02 in 153 6 02 in BLOWER BOX A Air in take clearance B Duct trim cove...

Страница 10: ...ROUTING Floor must be able to withstand a moving load of 5320 daN Minimum Opening Height 2 5m 98 5 in width 2 5m 98 5 in Maximum slope 30 degree STRAIGHT PATH Rigging wheels required PATH WITH 90 DEGR...

Страница 11: ...safety all removable items within the magnet room such as faucet handles drain covers switch box cover plates light fixture components mounting screws etc Must be non magnetic If you have a specific...

Страница 12: ...ng 4 Structural wall backing for Magnet Rundown Unit 5 Structural wall backing for Main Disconnect Panel 6 Structural wall backing for Magnet Monitor 7 Floor levelness area for Systems Cabinet Date Re...

Страница 13: ...ded to the structural elements and not to common screed for magnet anchoring table dock anchor hole VibroAcoustic Pad weight 8 kg 17 lbs each Seismic anchor holes 1346 53 in 673 26 5 in 250 9 8 in 175...

Страница 14: ...supplied and installed by the customer or his contractors For complete design and requirements specifications and guidelines refer to the pre installation manual system cooling cryogen venting wavegu...

Страница 15: ...xhaust Intake Vent MAGNET ROOM CONTROL ROOM RF Filter ON OFF Manual fan switches in parallel Ductwork Ductwork MAGNET ROOM VENTING REQUIREMENTS HVAC VENT REQUIREMENTS HVAC vendor must comply with Magn...

Страница 16: ...ow 30 l min 8 gpm Temperature rise at maximum flow Temperature rise at minimum flow Maximum inlet pressure of Chiller Cryo Compressor 690 kPa 100 psi Minimum inlet pressure of Chiller Cryo Compressor...

Страница 17: ...PIPE DETAIL MAGNET VENT ADAPTER Do not remove or modify the vent adaptor bolted to the magnet VENT PIPE 610 mm 24 in may be cut to a minimum of 100 mm 4 in VENTGLAS CONNECTOR WAVEGUIDE Additional pipe...

Страница 18: ...10 63 4 52 31 17 8 22 56 68 2 26 15 58 4 11 28 34 10 in 250mm 0 20 0 6 1 0 03 0 68 0 55 3 79 0 82 5 65 0 27 1 86 0 04 2 83 20 40 6 1 12 2 0 07 1 58 0 82 5 65 1 51 10 41 0 41 2 83 0 75 5 17 40 60 12 2...

Страница 19: ...n direct as possible otherwise may result in the need for greater than standard cable lengths refer to the interconnection diagram for maximum usable lengths point to point 8 Conduit turns to have lar...

Страница 20: ...ephone lines network connection Duplex hospital grade dedicated outlet 120 v emergency single phase power 15a Duplex hospital grade dedicated outlet 120 v single phase outlet routed through RF filter...

Страница 21: ...P SIGNA_EXPLORER WEB DWG A 03 Aug 2018 SIGNA EXPLORER SIGNA CREATOR Typical E3 Electrical Elevations 21 MAGNET ROOM EQUIPMENT ROOM 8 9 TBD TBD 5 4 7 9 9 8 CONTROL ROOM 5 4 3 2 TBD TBD TBD TBD TBD TBD...

Страница 22: ...THE FLOOR NOT TO SCALE Removable coverplate DUCT ON THE WALL Date Rev 24 EN MRI TYP SIGNA_EXPLORER WEB DWG A 03 Aug 2018 SIGNA EXPLORER SIGNA CREATOR Typical E4 Electrical Details 22 CABLE MANAGEMENT...

Страница 23: ...E EMERGENCY OFF BUTTONS ARE SUPPLIED WITH GE MDP OPTION EMERGENCY OFF BUTTONS ARE CUSTOMER SUPPLIED IF GE MDP OPTION NOT USED CIRCUIT BREAKERS ARE PROVIDED FOR PDU CRYO COOLER COMPRESSOR CHILLER GRADI...

Страница 24: ...5 75m 13 94 51 67 ft 17 98 m 59 ft 9 56 m 31 ft 12 5 m 41 ft 12 8m 42 ft 17 4m 57 ft 2 55 16 13m 8 35 52 9 ft 12 2m 40 ft 21 00 m 68 ft 4 3 11 3m 14 1 37 1 ft GOC MAGNET ROOM CONTROL ROOM EQUIPMENT RO...

Отзывы: